Exam 8: Managing Risk
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
involves regularly reviewing the risk management matrix throughout the project.
(Multiple Choice)
4.8/5
(33)
Addressing risks will increase the chances of accomplishing the project objective.
(Multiple Choice)
4.7/5
(33)
The risks should be those that are somewhat likely to occur and/or can have a significant positive impact on accomplishing the project objective.
(True/False)
4.7/5
(44)
Managing risk includes taking action to foster the likelihood of occurrence or the impact of such unfavorable events.
(True/False)
4.8/5
(34)
The project team should not change the estimated impacts of previously identified risks as the project progresses.
(True/False)
4.8/5
(31)
A risk is an uncertain event that, if it occurs, can jeopardize accomplishing the project objective.
(True/False)
4.9/5
(41)
includes taking action to prevent or minimize the likelihood of occurrence or the impact of such unfavorable events.
(Multiple Choice)
4.7/5
(28)
Track and document which risks and the impact of those risks.
(Multiple Choice)
4.9/5
(43)
Project prices and budgets should include to pay for additional costs associated with implementing response plans.
(Multiple Choice)
4.8/5
(43)
are a good forum for regularly reviewing, updating, and addressing risks.
(Multiple Choice)
4.7/5
(39)
Risks may change as the project progresses and should be reflected in
(Multiple Choice)
4.7/5
(25)
involves identifying, assessing, and responding to project risks in order to minimize the likelihood of occurrence and/or potential impact of adverse events on the accomplishment of the project objective.
(Multiple Choice)
4.8/5
(45)
involves determining the likelihood that the risk event will occur and the degree of impact the event will have on the project objective.
(Multiple Choice)
4.9/5
(35)
Waiting for unfavorable events to occur and then reacting to them
(Multiple Choice)
4.9/5
(43)
The project manager needs to set the tone for encouraging open and timely discussion of risks among the project team.
(True/False)
4.9/5
(42)
involves developing an action plan to reduce the likelihood of occurrence or potential impact of each risk, establishing a trigger point for when to implement the actions to address each risk, and assigning responsibility to specific individuals for implementing each response plan.
(Multiple Choice)
4.8/5
(42)
is a rating of low, medium, or high based on the expected level of change in completing the project's objective if the risk were to occur during the project.
(Multiple Choice)
4.9/5
(29)
Showing 21 - 40 of 45
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)