Exam 6: Resource Utilization
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
Resource utilization charts based on each activity's latest start time are said to be based
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
B
A resource requirements plan illustrates
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
C
Resource-limited scheduling is a method for
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
D
Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.
(Multiple Choice)
4.8/5
(29)
assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.
(Multiple Choice)
4.9/5
(37)
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. If the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done?
(Multiple Choice)
4.8/5
(35)
The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because
(Multiple Choice)
4.9/5
(37)
Which of following would allow for level resources on the project?
(Multiple Choice)
4.9/5
(41)
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. What is the least amount of time that the project can be completed and how many resources are required to complete the work?
(Multiple Choice)
4.7/5
(34)
Resource leveling, or smoothing, levels the resources so that
(Multiple Choice)
4.9/5
(33)
When several activities need the same limited resource at the same time, the activities with
(Multiple Choice)
4.9/5
(29)
The start of noncritical activities are delayed beyond their earliest start times but not beyond their latest start times) in order to
(Multiple Choice)
4.9/5
(38)
Why are activities drawn in a serial relationship in a network diagram?
(Multiple Choice)
4.8/5
(34)
Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to
(Multiple Choice)
4.9/5
(39)
If resources are to be considered in planning, it is necessary to
(Multiple Choice)
4.9/5
(35)
Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.
(True/False)
4.8/5
(27)
This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number. 

(Multiple Choice)
4.8/5
(28)
In resource-limited scheduling, the lower priority activities get delayed.How does the delaying of activities affect the project?
(Multiple Choice)
4.8/5
(33)
In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?
(Multiple Choice)
4.8/5
(37)