Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
In many cases, the customer states high-level requirements in the project charter or RFP, but the project team or the contractor may need to collect more information from the customer or end users to further refine the requirements.
Free
(True/False)
4.9/5
(29)
Correct Answer:
True
The customer may make unannounced visits to the contactor's facility or work.
Free
(True/False)
4.9/5
(39)
Correct Answer:
True
The work packages are at a level at which the wants to monitor and control the budget, and can collect data on actual costs and the value of the work completed during the performance of the project.
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
B
Having a written quality plan at the outset of a project is extremely beneficial because it guarantees against incurring additional costs and schedule extensions due to rework caused by work and deliverables that fail to meet quality requirements and customer expectations.
(True/False)
4.9/5
(31)
The at a level of a high degree of confidence that all the activities that need to be performed to produce the deliverable can be defined, the types and quantities of resources can be determined, and the associated activity durations and costs can be reasonably estimated.
(Multiple Choice)
4.9/5
(42)
The WBS usually indicates the organization or individual assigned responsibility for performance and completion of each work item.
(True/False)
4.9/5
(40)
If something is the statement of work, then it should be assumed that .
(Multiple Choice)
4.9/5
(39)
The responsibility assignment matrix may use a P to designate responsibility and an S to indicate responsibility for a specific work item.
(Multiple Choice)
4.9/5
(32)
Some projects have a set of activities that are repeated several times.
(True/False)
4.9/5
(39)
At the beginning of the project it might not be possible to define all of the requirements, work elements, and deliverables at a detailed level.
(True/False)
4.9/5
(36)
Expected benefits, which will result from implementation of the project and define success, establish
(Multiple Choice)
4.9/5
(33)
The is a communication tool for the project team because it shows who is responsible for each activity and how each person's work fits into the overall project.
(Multiple Choice)
4.7/5
(33)
Standard subnetworks should be developed for those portions of projects for which
(Multiple Choice)
4.7/5
(41)
An activity, also referred to as a task, is a defined piece of work that consumes effort by people and not necessarily time.
(True/False)
4.8/5
(35)
Using the work breakdown structure, the individual or team responsible for each work package must next define all the specific activities that need to be performed to produce the end item or deliverable for the work package.
(True/False)
4.9/5
(28)
Multiple individuals should be designated the lead, or primary, responsibility for each work item.
(True/False)
4.8/5
(32)
The work breakdown structure can include specifications regarding size, color, weight, or performance parameters, such as speed, uptime, throughput, processing time, or operating temperature range, that the project result must satisfy.
(True/False)
4.7/5
(35)
The project objective must be clearly defined and agreed upon by the
(Multiple Choice)
4.8/5
(31)
Showing 1 - 20 of 129
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)