Exam 3: Developing Project Proposals
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
A specific proposed solution should be suggested for the customer's need.
Free
(True/False)
4.8/5
(32)
Correct Answer:
False
Costs of escalation are costs associated with the increased costs for materials and wages in a long term project.
Free
(True/False)
4.9/5
(31)
Correct Answer:
True
An RFP says that the contract planned is to be fixed price.The project is well-defined and low risk.The contractor should bid based upon the contract type and risk level.
Free
(True/False)
4.8/5
(37)
Correct Answer:
True
The bid or no-bid decision is made on the capability to develop a quality proposal as well as the capability to complete the project if the contractor wins the bid.
(True/False)
4.8/5
(41)
As soon as a contractor finds out it is the winner, it can start working on the project.
(True/False)
4.9/5
(33)
The amount of profit on a project is adjusted depending upon the amount of competition for a project.
(True/False)
4.8/5
(36)
Establishing and building trust is key to developing effective and successful relationships with clients and partners.
(True/False)
4.8/5
(24)
Describe the differences between a complex proposal and a simplified proposal.
(Not Answered)
This question doesn't have any answer yet
The type of contract where the customer and the contractor agree on a price for the proposed work is
(Multiple Choice)
4.9/5
(33)
It is illegal for the contractor to overstate the hours or costs.
(True/False)
4.8/5
(26)
Materials that would be used for a construction project are
(Multiple Choice)
4.8/5
(35)
A contractor that is entering a similar but new field should plan a smaller profit to increase chances of winning the project.
(True/False)
4.9/5
(37)
Submitting a proposal that meets the customer's statement of work and requirements is all that is needed to secure a contract.
(True/False)
4.9/5
(30)
Good pre-RFP marketing helps a contractor to know if funds will be available for a project in an RFP.
(True/False)
4.8/5
(44)
The total dollar value approach is the ratio of the total dollar value of proposals that the contractor won as a percentage of the total dollar value of all the proposals the contractor submitted to various customers during a specific time period.
(True/False)
4.9/5
(34)
Helping customers identify needs, even if they are needs your company cannot help them address, is a way to position your company to win future contracts.
(True/False)
4.9/5
(40)
Fixed-price contracts are most appropriate for projects that
(Multiple Choice)
4.8/5
(38)
Showing 1 - 20 of 112
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)