Exam 5: Developing the Schedule
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
Latest finish time LF) is the latest time by which a specific activity must be
Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
B
As the project progresses, the actual finish times AFs) of completed activities will determine
Free
(Multiple Choice)
4.8/5
(28)
Correct Answer:
A
It is a good practice to have the person who will be responsible for performing a specific activity estimate the duration that other resources would need to complete that activity.
Free
(True/False)
4.9/5
(36)
Correct Answer:
False
Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then
(Multiple Choice)
5.0/5
(38)
With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:
(Multiple Choice)
4.8/5
(42)
Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
(Multiple Choice)
4.8/5
(31)
The development team develops, delivers, and demonstrates during a sprint.
(Multiple Choice)
4.9/5
(30)
The estimated duration for each activity is indicated by a bar spanning the period
(Multiple Choice)
4.9/5
(30)
Throughout a project, changes may occur that have an impact on the schedule.
(True/False)
4.7/5
(32)
The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.
(True/False)
4.9/5
(38)
Earliest finish time EF) is the earliest time by which a specific activity can be completed, calculated
(Multiple Choice)
4.7/5
(30)
The estimated types and quantities of resources required for an activity together with the availability of those resources will influence the
(Multiple Choice)
4.8/5
(42)
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
(Multiple Choice)
4.8/5
(34)
Negative slack indicates a lack of slack over the entire project and the amount of time
(Multiple Choice)
4.9/5
(37)
The estimated duration for each activity must be the total elapsed time,
(Multiple Choice)
4.9/5
(24)
People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,
(Multiple Choice)
4.9/5
(34)
When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.
(True/False)
4.7/5
(32)
Schedule control involves four steps.List the four steps in order.
(Short Answer)
4.7/5
(32)
A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.
(True/False)
4.7/5
(40)
Showing 1 - 20 of 86