Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
A common reason for cost overruns in a project is a low initial estimate of project cost.
(True/False)
5.0/5
(35)
Activity-based costing is based on the notion that projects consume activities and activities consume resources.
(True/False)
4.8/5
(34)
The term expedited cost has the same meaning as crashing cost in the project management milieu.
(True/False)
4.8/5
(28)
A budgeting method that assigns costs first to activities and then to projects based on each project's use of resources is:
(Multiple Choice)
4.9/5
(40)
Activity-based costing and bottom-up budgeting share the step of:
(Multiple Choice)
4.8/5
(30)
It began as a simple macro that would extract grades and post them on a web site,but once the web programmer began the work,he became obsessed with various charting features,grade summaries,and reports that could be added to make this the grandest web site in the tri-county area.As 2 hours of programming work grew to 20 and then 80,he knew that the client wouldn't be happy with the cost overrun.The only comment he mumbled as he finished his work was:
(Multiple Choice)
4.7/5
(41)
"If the weather holds and the utility service has correctly marked the location of the gas,telephone,and electric lines zigzagging across my property,I should be able to install the accent lighting in my back yard in an afternoon's time," the do-it-yourselfer commented to his jealous (and skeptical)neighbor.The only reply he received was his neighbor's,"Good luck with all that,I remember reading somewhere that:
(Multiple Choice)
4.9/5
(38)
What learning rate is being demonstrated if the first unit takes 25 hours and the seventh unit takes 22 hours to complete?
(Multiple Choice)
4.8/5
(38)
"If anything can go wrong it often will" is an articulation of:
(Multiple Choice)
4.9/5
(36)
Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
(True/False)
4.8/5
(38)
What is a time-phased budget and how does it help a project manager control costs?
(Essay)
4.8/5
(48)
An activity with a learning rate of 0.85 takes 25 hours for the first iteration.How long will it take to complete this task for the 15th time?
(Multiple Choice)
4.8/5
(38)
Unplanned costs incurred when steps are taken to speed up a project's completion are called:
(Multiple Choice)
4.7/5
(37)
If it takes 40 hours to complete the first unit and the company knows from experience that the learning rate should be 0.80,how fast can they be expected to finish all twelve units?
(Multiple Choice)
4.8/5
(29)
When properly performed,bottom-up budgeting has the disadvantage of:
(Multiple Choice)
4.9/5
(39)
Showing 61 - 80 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)