Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management?103 Questions
Exam 2: The Organizational Context: Strategy,Structure,and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building,Conflict,and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
An order of magnitude estimate is usually more accurate than a ballpark estimate.
(True/False)
4.9/5
(28)
Normal conditions,by definition,occur the vast majority of the time in project management.
(True/False)
4.8/5
(32)
When asked to provide an estimate of an irrigation system,Pete looked from one end of the field to the other,licked a finger and held it in the air,squinted into the sun and said $25,000,give or take 30%.The technique employed for cost estimation is:
(Multiple Choice)
4.9/5
(49)
Poor initial scope development and work breakdown structure often creates cost overruns that are attributable to:
(Multiple Choice)
4.8/5
(35)
What is the total project budget for design in this time-phased budget? Activity Tuly August September October November RFP 34,721 Analysis 11,049 33,655 34,388 Design 33,718 34,474 26,759 36,328 Coding 7,713 34,905 40,244 Testing 40,916 896 Training 20,958 9,327 Roll-Out 8,186
(Multiple Choice)
4.9/5
(33)
Whether it is the Boeing V-22 Osprey or a simple storm door installation for a do-it-yourselfer,nothing is ever completed as quickly or as cheaply as initial estimates due to:
(Multiple Choice)
4.8/5
(35)
The project management research in brief titled "Delusion and Deception Taking Place in Large Infrastructure Projects," describes three reasons that cost overruns occur in large infrastructure project work.Briefly describe these three reasons
(Essay)
4.8/5
(35)
Acme is exploring two locations for a new plant to supply product for a government contract.They dispatch a team of industrial engineers and cost estimators to the Minneapolis-St.Paul area of Minnesota and to Kennewick-Pasco-Richland area in Washington.After conducting some tests,the teams return with some unusual findings,the Minneapolis-St.Paul workers seem to obey classic learning effect rules; their learning rate is 80% and is based on a doubling of output.They are much slower than their counterparts at the other site; it is estimated that the first batch units they assemble will take them 700 hours.The workforce in the Kennewick-Pasco-Richland area is much faster; their first batch will take only 470 hours.Strangely,these workers also exhibit learning effects,but their learning is based on a tripling of output rather than the traditional doubling and their rate is 78%.How many batches must be made before Minneapolis-St.Paul's time falls below Kennewick-Pasco-Richland's?
(Essay)
4.9/5
(37)
Which of the following is NOT contained in a typical time-phased budget?
(Multiple Choice)
4.8/5
(43)
What is the cumulative project budget for September in this time-phased budget? Activity Tuly August September October November RFP 34,721 Analysis 11,049 33,655 34,388 Design 33,718 34,474 26,759 36,328 Coding 7,713 34,905 40,244 Testing 40,916 896 Training 20,958 9,327 Roll-Out 8,186
(Multiple Choice)
5.0/5
(45)
Comparative estimates are more accurate than definitive estimates when applied to the same project.
(True/False)
4.8/5
(42)
What are four major categories of costs? Provide descriptions for each category.
(Essay)
4.9/5
(40)
What is the total project budget in this time-phased budget? Activity January February March April Survey 8,000 Design 5,250 4,500 Dirt 6,700 Foundation 12,550 Framing 37,250 Plumb 7,800 Wire 5,500
(Multiple Choice)
4.9/5
(39)
An early warning signal for the potential of an overdrawn budget is created when:
(Multiple Choice)
4.8/5
(38)