Exam 9: Project Scheduling: Pertcpm
Exam 1: Introduction53 Questions
Exam 2: An Introduction to Linear Programming56 Questions
Exam 3: Linear Programming: Sensitivity Analysis and Interpretation of Solution44 Questions
Exam 4: Linear Programming Applications in Marketing, finance, and OM52 Questions
Exam 5: Advanced Linear Programming Applications39 Questions
Exam 6: Distribution and Network Models62 Questions
Exam 7: Integer Linear Programming52 Questions
Exam 8: Nonlinear Optimization Models45 Questions
Exam 9: Project Scheduling: Pertcpm60 Questions
Exam 10: Inventory Models60 Questions
Exam 11: Waiting Line Models56 Questions
Exam 12: Simulation53 Questions
Exam 13: Decision Analysis80 Questions
Exam 14: Multicriteria Decisions42 Questions
Exam 15: Time Series Analysis and Forecasting53 Questions
Exam 16: Markov Processes36 Questions
Exam 17: Linear Programming: Simplex Method45 Questions
Exam 18: Simplex-Based Sensitivity Analysis and Duality32 Questions
Exam 19: Solution Procedures for Transportation and Assignment Problems39 Questions
Exam 20: Minimal Spanning Tree19 Questions
Exam 21: Dynamic Programming41 Questions
Select questions type
The main difference between CPM and PERT is
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
A
Three paths of a PERT network have these mean durations and variances in weeks:
Which path offers the greatest risk of overrunning a contract deadline of 48 weeks?

Free
(Essay)
5.0/5
(44)
Correct Answer:
Path 1: st = 1.658; z = 1.809; P(D > 48)= 3.5% Path 2: st = 2.345; z = 1.706; P(D > 48)= 4.4% Path 3: st = 1.095; z = 1.826; P(D > 48)= 3.4% Path 2 offers the greatest risk (but only by a small margin).
National Oil Company (NATOCO)must plan the shutdown of its Houston refinery for routine preventive maintenance.Each hour of downtime is lost production time and is very costly,so NATOCO wants the maintenance project completed in 22 hours.The PERT network below shows the precedence relationships of the activities involved in the project.The table gives the activity times and costs under normal operations and maximum crashing.
NATOCO wants to know the minimum cost of completing the maintenance project within the 22-hour period.Formulate and solve a linear program that will yield this information.


(Essay)
4.8/5
(39)
Joe King has ambitions to be mayor of Williston,North Dakota.Joe has determined the breakdown of the steps to the nomination and has estimated normal and crash costs and times for the campaign as follows (times are in weeks).
Joe is not a wealthy man and would like to organize a 16-week campaign at minimum cost.Write and solve a linear program to accomplish this task.


(Essay)
4.8/5
(34)
Shortening activity times,which is usually accomplished by adding resources to the project,is called crashing.
(True/False)
4.9/5
(34)
A project has the following activities,durations,costs,and precedence relationships:
Develop a time-cost trade-off analysis.Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost.Determine each step's cost and the duration of the project.

(Essay)
4.9/5
(34)
The critical path for this network is A - E - F,and the project completion time is 22 weeks.
If a deadline of 17 weeks is imposed,give the linear programming model for the crashing decision.


(Essay)
4.8/5
(31)
When activity times are uncertain,an activity's most likely time is the same as its expected time.
(True/False)
4.7/5
(34)
When activity times are uncertain,total project time is normally distributed by considering the overall mean being equal to the sum of the means of all of the critical activities.
(True/False)
4.9/5
(44)
It is normal for activities on the critical path to be delayed without delaying the entire project.
(True/False)
4.7/5
(33)
Use the following network of related activities with their duration times (weeks)to complete a row for each activity under the column headings below.



(Essay)