Exam 16: Short-Term Scheduling

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Which of the following is NOT tracked by scheduling optimization systems used in retail stores?

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

A

Identify the major disadvantages of the Gantt load chart.

Free
(Essay)
4.8/5
(28)
Correct Answer:
Verified

It does not account for production variability,such as unexpected breakdowns or human errors that require reworking a job.Consequently,the chart must be updated regularly to account for new jobs and revised time estimates.

What is finite capacity scheduling (FCS)?

Free
(Essay)
4.8/5
(33)
Correct Answer:
Verified

FCS is computerized short-term scheduling that overcomes the disadvantages of rule-based systems by providing the user with graphical interactive computing.

EDD stands for what?

(Multiple Choice)
4.8/5
(35)

Sequencing (or dispatching):

(Multiple Choice)
4.8/5
(33)

Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2).The processing times are given in the table below. a.What is the optimal sequence? b.What is the total flow time for this sequence? Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2).The processing times are given in the table below. a.What is the optimal sequence? b.What is the total flow time for this sequence?

(Essay)
5.0/5
(39)

Finite capacity scheduling provides the user with graphical interactive computing,which is the technique's primary advantage over rule-based scheduling.

(True/False)
4.9/5
(30)

The emergency room at a hospital estimates the following requirements for registered nurses (RNs)for the late night shift each week.Nurses work four consecutive days,then have off three days. The emergency room at a hospital estimates the following requirements for registered nurses (RNs)for the late night shift each week.Nurses work four consecutive days,then have off three days.    Perform cyclical scheduling on the data.(Note that you must identify three-day patterns of minimum requirements).How many RNs are required? How much extra capacity is required? Perform cyclical scheduling on the data.(Note that you must identify three-day patterns of minimum requirements).How many RNs are required? How much extra capacity is required?

(Essay)
4.8/5
(37)

What is the priority rule that sequences jobs using the smallest ratio of due date from today to processing time?

(Multiple Choice)
4.8/5
(33)

The critical ratio sequencing rule prioritizes the jobs based on the importance or value of the customers who have placed the orders.

(True/False)
4.7/5
(31)

The jobs listed below need to be completed.Assume that it is now day 140.If the jobs are sequenced according to the longest processing time rule,what is the lateness of job A? The jobs listed below need to be completed.Assume that it is now day 140.If the jobs are sequenced according to the longest processing time rule,what is the lateness of job A?

(Multiple Choice)
5.0/5
(34)

The short-term scheduling activity called "loading":

(Multiple Choice)
4.8/5
(34)

Because of the significance of labor in the scheduling of services,behavioral and social issues,wage and hour laws,and union contracts all complicate the scheduling process.

(True/False)
4.9/5
(28)

Eight jobs have been sequenced at a single work center.Total processing time for the eight jobs is 34 hours,and total flow time for the sequence is 85 hours.For this schedule,utilization is ________ and the average number of jobs in the system is ________.

(Multiple Choice)
4.7/5
(29)

The priority rule that appears fair to customers in service systems is ________.

(Short Answer)
4.8/5
(38)

Five jobs are waiting for processing through two work centers.Their processing time (in minutes)at each work center is contained in the table below.Each job requires work center Sigma before work center Delta.According to Johnson's rule,what sequence of jobs will minimize the completion time for all jobs? Five jobs are waiting for processing through two work centers.Their processing time (in minutes)at each work center is contained in the table below.Each job requires work center Sigma before work center Delta.According to Johnson's rule,what sequence of jobs will minimize the completion time for all jobs?

(Multiple Choice)
4.8/5
(46)

Which of the following dispatching rules tends to minimize job flow time?

(Multiple Choice)
4.8/5
(37)

The jobs listed below need to be completed.Assume that it is now day 140.If the jobs are sequenced according to the shortest processing time rule,what is the average completion time? The jobs listed below need to be completed.Assume that it is now day 140.If the jobs are sequenced according to the shortest processing time rule,what is the average completion time?

(Multiple Choice)
4.8/5
(31)

Which of the following is not an effectiveness criterion for scheduling?

(Multiple Choice)
4.9/5
(28)

Five welding jobs are waiting to be processed.Their processing times and due dates are given below.Using the critical ratio dispatching rule,in which order should the jobs be processed? All dates are specified as days from today. Five welding jobs are waiting to be processed.Their processing times and due dates are given below.Using the critical ratio dispatching rule,in which order should the jobs be processed? All dates are specified as days from today.

(Multiple Choice)
4.8/5
(39)