Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500,what is the crash cost per period?

Free
(Multiple Choice)
4.8/5
(28)
Correct Answer:
Verified

A

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.

Free
(Multiple Choice)
5.0/5
(32)
Correct Answer:
Verified

A

What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept.11,2001?

Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
Verified

E

Which of the following projects were completed by Bechtel?

(Multiple Choice)
4.8/5
(35)

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below. Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?

(Essay)
4.8/5
(30)

Identify each of the purposes of project scheduling.

(Essay)
4.8/5
(42)

A partially solved PERT problem is detailed in the table below.Times are given in weeks. A partially solved PERT problem is detailed in the table below.Times are given in weeks.    a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above. b.Which activities form the critical path? c.What is the estimated time of the critical path? d.What are the project variance and the project standard deviation? e.What is the probability of completion of the project after week 40? a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above. b.Which activities form the critical path? c.What is the estimated time of the critical path? d.What are the project variance and the project standard deviation? e.What is the probability of completion of the project after week 40?

(Essay)
4.8/5
(31)

Define slack time.

(Short Answer)
4.8/5
(36)

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings.

(Essay)
4.7/5
(28)

The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline. II.The job is typical and familiar to the existing organization. III.The work contains interrelated tasks requiring specialized skills. IV.The project is temporary but unimportant to long-term organizational success. V.The project cuts across organizational lines.

(Multiple Choice)
4.8/5
(40)

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000,what is the crash cost per period?

(Multiple Choice)
4.7/5
(29)

________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.

(Short Answer)
4.8/5
(35)

The phases of project management are:

(Multiple Choice)
4.7/5
(29)

A(n)________ divides a project into more and more detailed components.

(Short Answer)
4.8/5
(38)

The time an activity will take assuming very unfavorable conditions is:

(Multiple Choice)
4.8/5
(38)

A project organization works best for an organization when the project resides in only one of its functional areas.

(True/False)
4.8/5
(32)

A network consists of the activities in the following list.Times are given in weeks. A network consists of the activities in the following list.Times are given in weeks.    a.Draw the network diagram. b.Calculate the ES,EF,LS,LF,and Slack for each activity. c.What is project completion time? a.Draw the network diagram. b.Calculate the ES,EF,LS,LF,and Slack for each activity. c.What is project completion time?

(Essay)
4.8/5
(36)

A project being analyzed by PERT has 60 activities,13 of which are on the critical path.If the estimated time along the critical path is 214 days with a project variance of 100,what is the probability that the project will take 224 days or more to complete?

(Multiple Choice)
4.8/5
(30)

Activity D on a CPM network has predecessors B and C,and has successor F.D has duration 6.B's earliest finish is 18,while C's is 20.F's late start is 26.Which of the following is definitely true?

(Multiple Choice)
4.8/5
(46)

Which of the following is NOT one of the phases of project management?

(Multiple Choice)
4.9/5
(22)
Showing 1 - 20 of 120
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)