Exam 18: Statistical Applications in Quality Management
Exam 1: Defining and Collecting Data189 Questions
Exam 3: Numerical Descriptive Measures184 Questions
Exam 4: Basic Probability156 Questions
Exam 5: Discrete Probability Distributions218 Questions
Exam 6: The Normal Distribution and Other Continuous Distributions189 Questions
Exam 7: Sampling Distributions127 Questions
Exam 8: Confidence Interval Estimation196 Questions
Exam 9: Fundamentals of Hypothesis Testing: One-Sample Tests170 Questions
Exam 10: Two-Sample Tests210 Questions
Exam 11: Analysis of Variance130 Questions
Exam 12: Chi-Square Tests and Nonparametric Tests175 Questions
Exam 13: Simple Linear Regression213 Questions
Exam 14: Introduction to Multiple Regression337 Questions
Exam 15: Multiple Regression Model Building96 Questions
Exam 16: Time-Series Forecasting165 Questions
Exam 17: A Roadmap for Analyzing Data303 Questions
Exam 18: Statistical Applications in Quality Management130 Questions
Exam 19: Decision Making126 Questions
Exam 20: Index Numbers44 Questions
Exam 21: Chi-Square Tests for the Variance or Standard Deviation11 Questions
Exam 22: Mcnemar Test for the Difference Between Two Proportions Related Samples15 Questions
Exam 25: The Analysis of Means Anom2 Questions
Exam 23: The Analysis of Proportions Anop3 Questions
Exam 24: The Randomized Block Design85 Questions
Exam 26: The Power of a Test41 Questions
Exam 27: Estimation and Sample Size Determination for Finite Populations13 Questions
Exam 28: Application of Confidence Interval Estimation in Auditing13 Questions
Exam 29: Sampling From Finite Populations20 Questions
Exam 30: The Normal Approximation to the Binomial Distribution27 Questions
Exam 31: Counting Rules14 Questions
Exam 32: Lets Get Started Big Things to Learn First33 Questions
Select questions type
TABLE 18-8
Recently,a university switched to a new type of computer-based registration.The registrar is concerned with the amount of time students are spending on the computer registering under the new system.She decides to randomly select 8 students on each of the 12 days of the registration and determine the time each spends on the computer registering.The range,mean,and standard deviation of the times required to register are in the table that follows.
-Referring to Table 18-8,an
chart is to be used for the time required to register.The lower control limit for this data set is ________,while the upper control limit is ________.


(Short Answer)
4.8/5
(39)
TABLE 18-9
The manufacturer of canned food constructed control charts and analyzed several quality characteristics.One characteristic of interest is the weight of the filled cans.The lower specification limit for weight is 2.95 pounds.The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production.
-Referring to Table 18-9,an R chart is to be constructed for the weight.The upper control limit for this data set is ________.

(Short Answer)
4.9/5
(35)
TABLE 18-2
A political pollster randomly selects a sample of 100 voters each day for 8 successive days and asks how many will vote for the incumbent.The pollster wishes to construct a p chart to see if the percentage favoring the incumbent candidate is too erratic.
-Referring to Table 18-2,what is the numerical value of the center line for the p chart?

(Multiple Choice)
4.8/5
(44)
TABLE 18-4
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds)is too erratic and adversely affects expected profits.The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours.The sample mean and range for each hour are listed below.
She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds,respectively.
-True or False: The p chart is a control chart used for monitoring the proportion of items that meet given specifications.

(True/False)
4.9/5
(40)
TABLE 18-4
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds)is too erratic and adversely affects expected profits.The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours.The sample mean and range for each hour are listed below.
She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds,respectively.
-Referring to Table 18-4,suppose the supervisor constructs an R chart to see if the variability in collection times is in-control.What are the lower and upper control limits for this R chart?

(Multiple Choice)
4.8/5
(31)
TABLE 18-5
A manufacturer of computer disks took samples of 240 disks on 15 consecutive days.The number of disks with bad sectors was determined for each of these samples.The results are in the table that follows.
-Referring to Table 18-5,a p control chart is to be made for these data.The estimate of the standard error of the proportion of disks with bad sectors is ________.

(Short Answer)
4.7/5
(30)
Maintaining the gains that have been made with a revised process in the long term by avoiding potential problems that can occur when a process is changed involves which part of the DMAIC process?
(Multiple Choice)
4.8/5
(38)
TABLE 18-10
Below is the number of defective items from a production line over twenty consecutive morning shifts.
-True or False: Referring to Table 18-10,the c chart suggests that the special cause of variation must be incorporated into the process to become part of the permanent ongoing process.

(True/False)
4.9/5
(41)
Which of the following best measures the ability of a process to consistently meet specified customer-driven requirements?
(Multiple Choice)
4.8/5
(35)
TABLE 18-4
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds)is too erratic and adversely affects expected profits.The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours.The sample mean and range for each hour are listed below.
She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds,respectively.
-Referring to Table 18-4,suppose the supervisor constructs an
chart to see if the process is in-control.What are the lower and upper control limits of this chart?


(Multiple Choice)