Exam 22: Scheduling
Exam 1: Operations Management58 Questions
Exam 2: Quality Management74 Questions
Exam 3: Statistical Process Control112 Questions
Exam 4: Operational Decision-Making Tools: Acceptance Sampling28 Questions
Exam 5: Product Design83 Questions
Exam 6: Service Design80 Questions
Exam 7: Processes and Technology73 Questions
Exam 8: Capacity and Facilities Design85 Questions
Exam 9: Operational Decision-Making Tools: Facility Location Models21 Questions
Exam 10: Human Resources79 Questions
Exam 11: Operational Decision-Making Tools: Work Measurement31 Questions
Exam 12: Project Management85 Questions
Exam 13: Supply Chain Management: Strategy and Design56 Questions
Exam 14: Global Supply Chain Procurement and Distribution69 Questions
Exam 15: Forecasting85 Questions
Exam 16: Inventory Management78 Questions
Exam 17: Operational Decision-Making Tools: Simulation15 Questions
Exam 18: The Sales and Operations Planning Process76 Questions
Exam 19: Operational Decision-Making Tools: Linear Programming29 Questions
Exam 20: Resource Planning82 Questions
Exam 21: Lean Systems78 Questions
Exam 22: Scheduling78 Questions
Select questions type
If the following jobs are sequenced according to the DDATE rule,then the mean tardiness (in days)for all jobs is (assume zero for today's date) 

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
B
Scheduling using the theory of constraints (TOC)requires that process batch sizes and transfer batch sizes always match.
Free
(True/False)
4.9/5
(32)
Correct Answer:
False
The shortest processing time (SPT)rule is most useful when the job shop is not congested.
Free
(True/False)
4.9/5
(34)
Correct Answer:
False
If the following jobs are sequenced according to the SPT rule,then job B is completed on day (assume zero for today's date) 

(Multiple Choice)
4.9/5
(29)
Scheduling specifies when labour,equipment and facilities are needed to produce a product.
(True/False)
5.0/5
(32)
The theory of constraints (TOC)approach to scheduling concentrates on scheduling the bottleneck resources.
(True/False)
4.7/5
(35)
If the following jobs are sequenced according to the DDATE rule,then the maximum job tardiness (in days)is (assume zero for today's date) 

(Multiple Choice)
4.7/5
(37)
Job-shop scheduling is usually performed by skilled machine operators.
(True/False)
4.8/5
(40)
Four products (1,2,3,and 4)must be processed on one of four machines (A,B,C,and D).The times required in minutes for each product on each machine are shown below:
If management assigns products to machines so that the total time to complete all jobs is minimized,then the time to complete Product 1 is

(Multiple Choice)
4.8/5
(34)
If the following jobs are sequenced according to the LPT rule,then the maximum job tardiness (in days)is (assume zero for today's date) 

(Multiple Choice)
5.0/5
(30)
The following set of jobs must be processed serially through a two-step system.The times at each process are in hours.If Johnson's Rule is used to sequence the jobs then the makespan time (in hours)for all jobs is 

(Multiple Choice)
4.9/5
(36)
If the following jobs are sequenced according to the DDATE rule,then job A would be completed on day (assume zero for today's date) 

(Multiple Choice)
4.7/5
(33)
The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is
(Multiple Choice)
4.9/5
(40)
The sequence in which jobs should be processed is determined using linear programming.
(True/False)
4.8/5
(34)
Typically,there are more options available when scheduling employees because labour is a very flexible resource.
(True/False)
4.9/5
(29)
If the following jobs are sequenced according to the SLACK rule,then the mean tardiness (in days)for all jobs is (assume zero for today's date) 

(Multiple Choice)
4.8/5
(32)
If a job is ahead of schedule,then its critical ratio (CR)will be
(Multiple Choice)
4.9/5
(35)
If the following jobs are sequenced according to the SPT rule,then the mean tardiness (in days)for all jobs is (assume zero for today's date) 

(Multiple Choice)
4.9/5
(43)
Gantt charts show the planned and yet to be completed activities against total activities.
(True/False)
4.7/5
(30)
Minimizing overtime is one of several objectives that could be considered when constructing a schedule.
(True/False)
5.0/5
(38)
Showing 1 - 20 of 78
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)