Exam 20: Resource Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

___ is a lot-sizing technique that orders for multiple demand periods and is referred to as

Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
Verified

B

Material requirements planning (MRP)is a useful for all of the following except

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

C

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,the periodic order quantity would be If each order cost $500 and the holding cost is $0.75 per item per period,the periodic order quantity would be

Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
Verified

A

Planned order releases at one level of a product structure generate gross requirements at the next level.

(True/False)
4.9/5
(44)

When is it appropriate to use material requirements planning (MRP)?

(Essay)
4.9/5
(35)

A forecast of dependent demand requirements is one of the major inputs into the MRP process.

(True/False)
4.9/5
(32)

ERP systems are only concerned with production and marketing processes.

(True/False)
4.8/5
(36)

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 4 would be If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 4 would be

(Multiple Choice)
4.8/5
(28)

The quantities reported on a master production schedule may reflect a combination of actual and forecasted demand.

(True/False)
4.7/5
(35)

Which of the following would not be used for an overloaded condition?

(Multiple Choice)
4.8/5
(36)

A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period. A firm has the following gross requirements for Item F.If ordering costs are $60 per order and carrying costs are $0.50 per period.   If EOQ lot sizing is used to set the minimum order quantity,then the planned order releases would be If EOQ lot sizing is used to set the minimum order quantity,then the planned order releases would be

(Multiple Choice)
4.8/5
(30)

A phantom bill of material is used

(Multiple Choice)
4.8/5
(37)

Given the following MRP matrix for Item E: Given the following MRP matrix for Item E:   The planned order releases for period 3 would be The planned order releases for period 3 would be

(Multiple Choice)
4.9/5
(35)

Given the following Product Structure Record: Given the following Product Structure Record:   The number of E's required for each A would be The number of E's required for each A would be

(Multiple Choice)
4.9/5
(34)

The quantities displayed on a master production schedule represent production and not actual demand.

(True/False)
4.8/5
(32)

Single-source ERP systems are often easier to integrate than systems built using the best-in-breed approach.

(True/False)
4.8/5
(39)

What steps are necessary to effectively implement Enterprise Resource Planning (ERP)?

(Essay)
4.8/5
(28)

The application modules that comprise the ERP system are designed to support only customer relationship management processes.

(True/False)
4.8/5
(27)

Given the following MRP matrix for Item C: Given the following MRP matrix for Item C:   If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 1 would be If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Planned Order Release for period 1 would be

(Multiple Choice)
4.8/5
(43)

What is a bill of material?

(Essay)
4.8/5
(32)
Showing 1 - 20 of 82
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)