Exam 8: Capacity and Facilities Design

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The material storage space required for in-process inventory is typically larger in

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
Verified

D

The capacity cushion for a facility equals one minus utilization.

Free
(True/False)
4.8/5
(30)
Correct Answer:
Verified

True

A company has a target output rate of 40 units every five (5)hours when its line is fully operational.To achieve this target the firm must have a cycle time of

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
Verified

C

A flexible manufacturing system (FMS)combines flexibility with higher efficiency.

(True/False)
4.8/5
(35)

Shipbuilding is an example of production system requiring a process layout.

(True/False)
4.9/5
(28)

An assembly line consists of three workstations (WS)with each station's activity time as shown. An assembly line consists of three workstations (WS)with each station's activity time as shown.   The cycle time for this line is The cycle time for this line is

(Multiple Choice)
4.9/5
(32)

Cycle time refers to

(Multiple Choice)
4.9/5
(32)

Briefly list the disadvantages of a cellular layout.

(Essay)
4.7/5
(39)

Which of the following statements is most true?

(Multiple Choice)
4.9/5
(32)

A process layout groups similar activities together according to the functions they perform.

(True/False)
4.9/5
(34)

The cycle time refers to the maximum amount of time a product is allowed to spend at each workstation.

(True/False)
4.7/5
(30)

Cellular layouts reduce transit time and increase set-up.

(True/False)
4.8/5
(29)

Which of the following is not an "area" of disadvantage of cellular layouts?

(Multiple Choice)
4.9/5
(36)

One of the best known computerized packages available for designing process layouts is CRAFT.CRAFT stands for

(Multiple Choice)
4.9/5
(32)

What type of layout is commonly used in services? What are some of the objectives associated with service layouts?

(Essay)
4.9/5
(37)

With a product layout the purpose of line balancing is to equalize the amount of work at each workstation.

(True/False)
4.8/5
(42)

Briefly describe a cellular layout and its objectives.

(Essay)
5.0/5
(28)

The balance delay is calculated by subtracting efficiency in percent from one hundred.

(True/False)
4.7/5
(30)

Increasing capacity utilization beyond the best operating level results in diseconomies of scale.

(True/False)
4.7/5
(35)

Precedence requirements reflect physical restrictions on the order in which operations are performed in a product layout.

(True/False)
4.9/5
(35)