Exam 12: Demand Planning: Forecasting and Demand Management
Exam 1: Introduction to Managing Operations Across the Supply Chain40 Questions
Exam 2: Operations and Supply Chain Strategy25 Questions
Exam 3: Managing Processes and Capacity29 Questions
Exam 3: A: Process Mapping and Analysis31 Questions
Exam 4: Productprocess Innovation43 Questions
Exam 5: Manufacturing and Service Process Structures53 Questions
Exam 6: Managing Quality44 Questions
Exam 6: A: Quality Improvement Tools51 Questions
Exam 7: Managing Inventories32 Questions
Exam 8: Lean Systems57 Questions
Exam 9: Customer Service Management59 Questions
Exam 10: Sourcing and Supply Management50 Questions
Exam 11: Logistics Management39 Questions
Exam 12: Demand Planning: Forecasting and Demand Management44 Questions
Exam 13: Sales and Operations Planning36 Questions
Exam 14: Materials and Resource Requirements Planning33 Questions
Exam 15: Project Management34 Questions
Exam 15: A: Advanced Methods for Project Scheduling40 Questions
Exam 16: Sustainable Operations Management Preparing for the Future39 Questions
Select questions type
A master production schedule shows the beginning inventory is 50 units,the forecast is 200 units,and actual customer orders are 220 units.What is the quantity that is available to promise in period 1?
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
D
The following table shows capacity requirements data for making tabletops.
Which of the following is TRUE?

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
C
A master production schedule shows the following information:
Using a lot-for-lot rule,what is the MPS quantity for period 1?

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
B
The following table shows capacity requirements data for making Blodgetts.
A load profile would show:

(Multiple Choice)
4.8/5
(36)
A master production schedule shows the beginning inventory is 100 units,the forecast is 250 units,and actual customer orders are 400 units.Using a lot-for-lot rule,what is the MPS quantity for period 1?
(Multiple Choice)
4.8/5
(38)
MRP is a process that would be most applicable in which situation?
(Multiple Choice)
4.9/5
(32)
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers.The type of system Zanda should consider is known as:
(Multiple Choice)
4.9/5
(28)
Which of the following pieces of information is NOT contained in an MRP secondary report?
(Multiple Choice)
4.8/5
(36)
All of the following are outputs from an MRP system EXCEPT:
(Multiple Choice)
4.7/5
(38)
If the cumulative lead time is eight weeks,for a project to be feasible the MPS planning horizon must be:
(Multiple Choice)
4.8/5
(36)
A master production schedule shows the beginning inventory is 50 units,the forecast is 80 units,and actual customer orders are 70 units.Using a lot-for-lot rule,what is the MPS quantity for period 1?
(Multiple Choice)
4.8/5
(37)
A master production schedule shows the following information:
What is the number of items available to promise for period 2?

(Multiple Choice)
4.9/5
(36)
Significant changes in an MPS quantity several weeks into the planning horizon can:
(Multiple Choice)
4.7/5
(42)
A master production schedule shows the following information:
Using a lot-for-lot rule,what is the MPS quantity for week 4?

(Multiple Choice)
4.8/5
(35)
Showing 1 - 20 of 44
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)