Exam 14: Materials and Resource Requirements Planning
Exam 1: Introduction to Managing Operations Across the Supply Chain40 Questions
Exam 2: Operations and Supply Chain Strategy25 Questions
Exam 3: Managing Processes and Capacity29 Questions
Exam 3: A: Process Mapping and Analysis31 Questions
Exam 4: Productprocess Innovation43 Questions
Exam 5: Manufacturing and Service Process Structures53 Questions
Exam 6: Managing Quality44 Questions
Exam 6: A: Quality Improvement Tools51 Questions
Exam 7: Managing Inventories32 Questions
Exam 8: Lean Systems57 Questions
Exam 9: Customer Service Management59 Questions
Exam 10: Sourcing and Supply Management50 Questions
Exam 11: Logistics Management39 Questions
Exam 12: Demand Planning: Forecasting and Demand Management44 Questions
Exam 13: Sales and Operations Planning36 Questions
Exam 14: Materials and Resource Requirements Planning33 Questions
Exam 15: Project Management34 Questions
Exam 15: A: Advanced Methods for Project Scheduling40 Questions
Exam 16: Sustainable Operations Management Preparing for the Future39 Questions
Select questions type
If a project path has an expected duration of 10 days and a standard deviation of three days,what is the probability that the path will be completed in 13 days or less?
Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
D
A simple sequential project (each task must be completed before the next one can begin)has the time estimates (in days)shown below:
What is the likelihood the project will be completed in 10 days?

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
D
Given the tasks,estimated durations,and crash costs shown below,what is the total cost of the steps needed to provide the cheapest way to reduce the project length by three days? 

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
B
Given the project data below,what is the expected length of path A,B,C? 

(Multiple Choice)
4.8/5
(38)
A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days)shown in the table below.Complete the table and determine the probability that the project will be completed in 20 days or less. 

(Multiple Choice)
4.9/5
(37)
Given the tasks,estimated durations,and crash costs shown below,which task would you crash first? 

(Multiple Choice)
4.8/5
(37)
The four tasks below must be completed in order (a single path of tasks).Given the task information,what is the probability that the path of tasks will be completed in 20 days or less? 

(Multiple Choice)
4.8/5
(46)
If a project path has an expected duration of 10 days and a standard deviation of three days,what is the probability that the path will be completed in 10 days or less?
(Multiple Choice)
5.0/5
(29)
Which of the following statements best describes "crash cost"?
(Multiple Choice)
4.8/5
(33)
Task X has a most likely duration of 10 days,a best-case duration of 8 days,and a worst-case duration of 15 days.What is the probability that it will be completed in 10 days or less?
(Multiple Choice)
4.8/5
(35)
A simple sequential project (each task must be completed before the next one can begin)has the time estimates (in days)shown below:
What is the probability that the project will be completed within 8.5 days? (Choose the closest answer.)

(Multiple Choice)
4.8/5
(26)
Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.
If Annie saves $40 for every hour she can reduce from her plan,what is her total net benefit from crashing this project by six hours?

(Multiple Choice)
4.8/5
(30)
Given the project plan shown below,which task has the largest standard deviation (uncertainty)relative to its expected duration (standard deviation divided by expected duration)? 

(Multiple Choice)
4.8/5
(28)
Given the tasks,estimated durations,and crash costs shown below,if the benefit to crash the project by each day is a maximum of $750,how many days would it be worthwhile to crash the project? 

(Multiple Choice)
4.9/5
(28)
Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.
Annie will save $40 for every hour she can reduce from her plan.Annie has decided to crash her project and use the money she saves to purchase a larger gift for Gwendolyn.Which task should she crash first?

(Multiple Choice)
4.8/5
(27)
Given the project data below,what is the standard deviation of durations for path A,B,C? 

(Multiple Choice)
4.9/5
(29)
Annie is planning a large surprise party for her sister Gwendolyn.She has developed the following plan,including estimates of the time (in hours)and cost necessary to perform each of the tasks required.
Annie will save $40 for every hour she can reduce from her plan.If Annie crashes only task A to its minimum duration,how much will she save on the project?

(Multiple Choice)
4.8/5
(35)
Given the project plan shown below,for each task assume that the best-case duration is 80 percent of the most likely duration,and the worst-case duration is 150 percent of the most likely duration.What is the expected completion time for the critical path? 

(Multiple Choice)
4.9/5
(41)
Which of the following statements is true regarding crash costs?
(Multiple Choice)
4.8/5
(40)
Given the tasks,estimated durations,and crash costs shown below,which task would you crash last in order to minimize the project length? 

(Multiple Choice)
4.8/5
(39)
Showing 1 - 20 of 33
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)