Exam 9: Project Scheduling: Pertcpm

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.

Free
(True/False)
4.8/5
(39)
Correct Answer:
Verified

False

Which is not a significant challenge of project scheduling?

Free
(Multiple Choice)
4.7/5
(39)
Correct Answer:
Verified

B

The variance in the project completion time is the sum of the variances of all activities in the project.

Free
(True/False)
4.9/5
(36)
Correct Answer:
Verified

False

Which of the following is always true about a critical activity?

(Multiple Choice)
4.8/5
(40)

Which of the following is a general rule for crashing activities?

(Multiple Choice)
4.8/5
(37)

The length of time an activity can be delayed without affecting the project completion time is the slack.

(True/False)
4.8/5
(29)

Explain how and why all successor activities must be considered when finding the latest finish time.

(Essay)
4.9/5
(39)

Arcs in a project network indicate

(Multiple Choice)
4.8/5
(30)

To determine how to crash activity times

(Multiple Choice)
4.9/5
(27)

Use the following network of related activities with their duration times to complete a row for each activity under the column headings below.  Use the following network of related activities with their duration times to complete a row for each activity under the column headings below.    \begin{array} { | c | c | c | c | c | c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Activity } \\ \text { Time } \end{array} & E S & L S & E F & L F & \text { Sack } & \begin{array} { c }  \text { Critical } \\ \text { Path? } \end{array} \\ \hline \mathrm { A } & & & & & & & & \\ \hline \mathrm { B } & & & & & & & & \\ \hline \mathrm { C } & & & & & & & & \\ \hline \mathrm { D } & & & & & & & & \\ \hline \mathrm { E } & & & & & & & & \\ \hline \mathrm { F } & & & & & & & & \\ \hline \mathrm { G } & & & & & & & & \\ \hline \mathrm { H } & & & & & & & & \\ \hline \end{array} Activity Immediate Predecessors Activity Time ES LS EF LF Sack Critical Path?

(Essay)
4.9/5
(28)

When activity times are uncertain, an activity's most likely time is the same as its expected time.

(True/False)
4.8/5
(33)

The earliest finish time for the final activity is the project duration.

(True/False)
4.8/5
(39)

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.  A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.    \begin{array} { | c | c | c | c | c | c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Precedence } \\ \text { Activities } \end{array} & \begin{array} { c }  \text { Activity } \\ \text { Time } \\ \text { (weeks) } \end{array} & E S & L S & E F & \text { LF } & \text { Slack } & \begin{array} { c }  \text { Critical } \\ \text { Path? } \end{array} \\ \hline \mathrm { A } & & & & & & & & \\ \hline \mathrm { B } & & & & & & & & \\ \hline \mathrm { C } & & & & & & & & \\ \hline \mathrm { D } & & & & & & & & \\ \hline \mathrm { E } & & & & & & & & \\ \hline \mathrm { F } & & & & & & & & \\ \hline \mathrm { G } & & & & & & & & \\ \hline \mathrm { H } & & & & & & & & \\ \hline \mathrm { I } & & & & & & & & \\ \hline \end{array}  Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in more than 28 weeks more or less than 50%? Activity Precedence Activities Activity Time (weeks) ES LS EF LF Slack Critical Path? Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in more than 28 weeks more or less than 50%?

(Essay)
4.8/5
(30)

For an activity with more than one immediate successor activity, its latest-finish time is equal to the

(Multiple Choice)
4.9/5
(40)

The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.

(True/False)
4.9/5
(42)

Name at least three managerial situations where answers are provided by project management solutions.

(Essay)
4.8/5
(32)

Constraints in the LP models for crashing decisions are required to compare the activity's earliest finish time with the earliest finish time of each predecessor.

(True/False)
4.8/5
(43)

PERT and CPM

(Multiple Choice)
4.8/5
(31)

Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 11. The latest finish time for activity H

(Multiple Choice)
4.8/5
(36)

Use the following network of related activities with their duration times to complete a row for each activity under the column headings below.  Use the following network of related activities with their duration times to complete a row for each activity under the column headings below.    \begin{array} { | c | c | c | c | c | c | c | c | c | }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Time } \\ \text { (weeks) } \end{array} & E S & L S & E F & L F & \text { Sack } & \begin{array} { c }  \text { Critical } \\ \text { Path? } \end{array} \\ \hline A & \\ \hline B & \\ \hline \mathrm{C} & \\ \hline \mathrm{D} & \\ \hline \mathrm{E} & \\ \hline \mathrm{F} & \\ \hline \mathrm{G} & \\ \hline \mathrm{H} & \\ \hline \mathrm{I} & \\ \hline \mathrm{J} & \\ \hline \end{array} Activity Immediate Predecessors Time (weeks) ES LS EF LF Sack Critical Path? A B

(Essay)
4.8/5
(35)
Showing 1 - 20 of 44
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)