A chart to show time lengths and sequences of project task activities was developed by?

(Multiple Choice)
4.8/5
(36)

Briefly describe the purpose and origins of the CPM and PERT project management techniques.

(Essay)
5.0/5
(34)

Which of the following is not a category of project management risk?

(Multiple Choice)
4.9/5
(26)

Three activities (A, B, and C) have crash costs per hour of $75, $50, and $100, respectively. Which of these activities should be crashed first?

(Multiple Choice)
4.9/5
(45)

An activity's early start time minus late start time is referred to as the activity's?

(Multiple Choice)
4.8/5
(33)

Which of the following is not likely to be an example of a project?

(Multiple Choice)
4.8/5
(45)

A(n) __________ is a temporary group activity designed to produce a unique product, service, or result.

(Short Answer)
4.8/5
(36)

The cost associated with reducing an activity duration is often referred to as a crash cost.

(True/False)
4.8/5
(38)

The second step to crash a project is?

(Multiple Choice)
4.7/5
(44)

In the t = (a + 4m + b)/6 calculation for expected activity completion time, the b refers to?

(Multiple Choice)
4.8/5
(38)

If an activity has a late start time of 10 and an early start time of 8, what is the activity's slack time?

(Multiple Choice)
4.7/5
(47)

When crashing a project, we should focus on activities with the lowest __________.

(Essay)
4.9/5
(44)

The time estimate that represents the time to complete the activity if everything goes wrong is the?

(Multiple Choice)
4.8/5
(32)

Software that is free or open source can be acceptable for small businesses facing relatively simple projects.

(True/False)
4.9/5
(39)

A project manager should?

(Multiple Choice)
4.8/5
(37)

The difference between the early start and late start times and the early finish and late finish times is referred to as?

(Multiple Choice)
4.9/5
(37)

When estimating the probability of completing a project by a given time, we often assume that project duration is distributed according to which statistical distribution?

(Multiple Choice)
4.9/5
(39)

A temporary group activity designed to produce a unique product, service, or result is referred to as a project.

(True/False)
4.9/5
(43)

Lack of communication among key personnel would be an example of what type of project risk?

(Multiple Choice)
4.8/5
(34)

PERT and CPM both seek to find the ________ sequence of activities in a project.

(Short Answer)
4.8/5
(30)