All critical path activities have a slack time greater than zero.

Free
(True/False)
4.8/5
(29)
Correct Answer:
Verified

False

Which of the following activities would likely be the best candidate for crashing?

Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
Verified

C

When evaluating a project risk, the project team should consider all of the following except?

Free
(Multiple Choice)
4.7/5
(37)
Correct Answer:
Verified

B

A project's critical path is the?

(Multiple Choice)
4.8/5
(26)

The bars in a Gantt chart show?

(Multiple Choice)
5.0/5
(38)

Poor supplier selection is an example of what type of project risk?

(Multiple Choice)
4.9/5
(17)

An activity has a normal duration of 4 hours and a crash time of 4 hours. How much crash time is available for this activity?

(Multiple Choice)
4.9/5
(31)

The longest sequence of activities in a project is referred to as the?

(Multiple Choice)
4.9/5
(36)

CPM, in a project management context, refers to the Critical Path Method.

(True/False)
4.7/5
(43)

Project risks that are either inside or outside of company control such as software integration problems are referred to as?

(Multiple Choice)
4.8/5
(35)

The fourth step in both the CPM and PERT approaches is?

(Multiple Choice)
4.8/5
(33)

The ___________ activity completion time could occur if "things go badly" with the activity.

(Short Answer)
4.8/5
(22)

Approximately what fraction of new software projects fail due to poor project planning?

(Multiple Choice)
4.8/5
(28)

Briefly summarize the Critical Path Method.

(Essay)
4.9/5
(38)

HyperOffice is an example of a cloud-based project management software solution.

(True/False)
4.8/5
(36)

Modern concerns of project managers include all of the following except?

(Multiple Choice)
4.9/5
(31)

A(n) ________ plan is developed to assess and manage project risks.

(Short Answer)
4.9/5
(41)

An activity with a slack time greater than zero?

(Multiple Choice)
4.8/5
(35)

The access to and delivery of information on an as-needed basis for a subscription fee is referred to as?

(Multiple Choice)
4.8/5
(39)

A noncritical path activity?

(Multiple Choice)
4.8/5
(46)