Exam 8: Supplement: Job Scheduling and Vehicle Routing
Exam 1: Operations Management, Processes, and Supply Chain Management134 Questions
Exam 2: Corporate Strategy, Performance, and Sustainability133 Questions
Exam 3: Product Design and Development134 Questions
Exam 4: Process Design and Capacity Management134 Questions
Exam 5: Customer Relationships and Customer Service134 Questions
Exam 6: Demand Management, Forecasting, and Aggregate Planning133 Questions
Exam 7: Independent Demand Inventory Management133 Questions
Exam 8: Material Flow Analysis and Facility Layouts134 Questions
Exam 8: Supplement: Job Scheduling and Vehicle Routing55 Questions
Exam 9: Lean Systems128 Questions
Exam 10: Managing Customer and Work Flows133 Questions
Exam 11: Managing Information Flowsmrp and Erp134 Questions
Exam 12: Managing Projects133 Questions
Exam 13: Six Sigma Quality Management134 Questions
Exam 13: Supplement: Statistical Quality Control65 Questions
Exam 14: Global Supply Management133 Questions
Exam 15: Location, Logistics, and Product Returns134 Questions
Exam 16: Integrating Processes Along the Supply Chain134 Questions
Select questions type
Describe the challenges faced when scheduling jobs in a product-focused production system.
Free
(Essay)
4.9/5
(41)
Correct Answer:
A successful answer should indicate the challenges such as keeping goods flowing through the system smoothly and maintaining a high degree of labor utilization.
Scheduling jobs into the future based upon job arrival date refers to?
Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
B
If I is the input rate and O is the output rate, what happens when I < O?
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
A
The primary scheduling issue in a product-focused facility is?
(Multiple Choice)
4.7/5
(40)
Short production run tend to result in _________ machine setups.
(Short Answer)
4.9/5
(34)
Short production runs have what effect on the amount of average WIP held?
(Multiple Choice)
4.9/5
(25)
Customer orders, in a flow management context, are often referred to as jobs.
(True/False)
4.7/5
(47)
Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB). J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average queue time of these jobs?
(Multiple Choice)
4.8/5
(39)
Having high quality schedules for delivery vehicles can lead to?
(Multiple Choice)
4.9/5
(31)
What type of rules determine which job to process next from a queue of waiting jobs?
(Multiple Choice)
4.9/5
(43)
Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB). J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average flow time of these jobs?
(Multiple Choice)
4.7/5
(36)
The ability to produce a wide variety of product types is referred to as?
(Multiple Choice)
4.9/5
(39)
Which job shop dispatch rule schedules the job with the shortest process time first?
(Multiple Choice)
4.8/5
(31)
Which job shop dispatch rule tends to work well to minimize average flow time?
(Multiple Choice)
4.7/5
(34)
Two jobs (J1 and J2) are to be scheduled on a single workcenter. J1 has a process time of 5 and J2 has a process time of 3. J1 has a due date of time 6 and J2 has a due date of time 7. If the jobs are scheduled by the EDD rule, in what order will they be processed?
(Multiple Choice)
4.9/5
(39)
Showing 1 - 20 of 55