Exam 12: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Activities on the critical path are referred to as?

(Multiple Choice)
4.8/5
(41)

If project completion times are normally distributed, what is the probability that the project will be completed by the mean project duration?

(Multiple Choice)
4.8/5
(28)

Which of the following activities would likely be the best candidate for crashing?

(Multiple Choice)
4.9/5
(30)

Three critical activities (A, B, and C) have crash costs per hour of $100, $150, and $200, respectively. Which of these activities should be crashed first?

(Multiple Choice)
4.8/5
(45)

Access to resources such as software on an as-needed basis for a subscription price or fee is referred to _________.

(Short Answer)
4.8/5
(36)

Project risks that are mostly within company control such as unrealistic activity time estimates are referred to as?

(Multiple Choice)
4.8/5
(35)

We are sometimes able to reduce the duration of a project by crashing the project.

(True/False)
4.8/5
(38)

The third step in both the CPM and PERT approaches is?

(Multiple Choice)
4.9/5
(30)

If an activity has a late start time of 10 and an early start time of 10, what is the activity's slack time?

(Multiple Choice)
5.0/5
(33)

Project risks that are within company control such as poor forecasting are referred to as?

(Multiple Choice)
5.0/5
(31)

PERT relies on all of the following time estimates except?

(Multiple Choice)
4.9/5
(34)

An activity with a slack time of zero?

(Multiple Choice)
4.8/5
(43)

A power outage leads to computers and software being temporarily unavailable. This is an example of what type of project risk?

(Multiple Choice)
4.8/5
(41)

The time estimate that represents the best estimate of time to complete the activity is the?

(Multiple Choice)
4.7/5
(38)

The use of unfamiliar software would be an example of what type of project risk?

(Multiple Choice)
4.8/5
(37)

The x-axis on a Gantt chart shows?

(Multiple Choice)
4.9/5
(41)

In the t = (a + 4m + b)/6 calculation for expected activity completion time, the m refers to?

(Multiple Choice)
4.9/5
(39)

___________ is the planning, scheduling, and controlling of resources to meet the specific goals of the project.

(Short Answer)
4.9/5
(36)

A list of possible substitute workers has been made in case a labor strike occurs. This would be an example of?

(Multiple Choice)
4.7/5
(36)

The use of strong contracts with suppliers, labor unions, etc., is an example of what?

(Multiple Choice)
4.9/5
(32)
Showing 81 - 100 of 133
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)