Exam 12: Managing Projects
Exam 1: Operations Management, Processes, and Supply Chain Management134 Questions
Exam 2: Corporate Strategy, Performance, and Sustainability133 Questions
Exam 3: Product Design and Development134 Questions
Exam 4: Process Design and Capacity Management134 Questions
Exam 5: Customer Relationships and Customer Service134 Questions
Exam 6: Demand Management, Forecasting, and Aggregate Planning133 Questions
Exam 7: Independent Demand Inventory Management133 Questions
Exam 8: Material Flow Analysis and Facility Layouts134 Questions
Exam 8: Supplement: Job Scheduling and Vehicle Routing55 Questions
Exam 9: Lean Systems128 Questions
Exam 10: Managing Customer and Work Flows133 Questions
Exam 11: Managing Information Flowsmrp and Erp134 Questions
Exam 12: Managing Projects133 Questions
Exam 13: Six Sigma Quality Management134 Questions
Exam 13: Supplement: Statistical Quality Control65 Questions
Exam 14: Global Supply Management133 Questions
Exam 15: Location, Logistics, and Product Returns134 Questions
Exam 16: Integrating Processes Along the Supply Chain134 Questions
Select questions type
If project completion times are normally distributed, what is the probability that the project will be completed by the mean project duration?
(Multiple Choice)
4.8/5
(28)
Which of the following activities would likely be the best candidate for crashing?
(Multiple Choice)
4.9/5
(30)
Three critical activities (A, B, and C) have crash costs per hour of $100, $150, and $200, respectively. Which of these activities should be crashed first?
(Multiple Choice)
4.8/5
(45)
Access to resources such as software on an as-needed basis for a subscription price or fee is referred to _________.
(Short Answer)
4.8/5
(36)
Project risks that are mostly within company control such as unrealistic activity time estimates are referred to as?
(Multiple Choice)
4.8/5
(35)
We are sometimes able to reduce the duration of a project by crashing the project.
(True/False)
4.8/5
(38)
If an activity has a late start time of 10 and an early start time of 10, what is the activity's slack time?
(Multiple Choice)
5.0/5
(33)
Project risks that are within company control such as poor forecasting are referred to as?
(Multiple Choice)
5.0/5
(31)
A power outage leads to computers and software being temporarily unavailable. This is an example of what type of project risk?
(Multiple Choice)
4.8/5
(41)
The time estimate that represents the best estimate of time to complete the activity is the?
(Multiple Choice)
4.7/5
(38)
The use of unfamiliar software would be an example of what type of project risk?
(Multiple Choice)
4.8/5
(37)
In the t = (a + 4m + b)/6 calculation for expected activity completion time, the m refers to?
(Multiple Choice)
4.9/5
(39)
___________ is the planning, scheduling, and controlling of resources to meet the specific goals of the project.
(Short Answer)
4.9/5
(36)
A list of possible substitute workers has been made in case a labor strike occurs. This would be an example of?
(Multiple Choice)
4.7/5
(36)
The use of strong contracts with suppliers, labor unions, etc., is an example of what?
(Multiple Choice)
4.9/5
(32)
Showing 81 - 100 of 133
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)