Exam 8: Scheduling Resources and Costs

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?

(Multiple Choice)
4.7/5
(33)

After constructing a project network based on technical constraints and reviewing resource requirements throughout the project, a project manager realizes many peaks and valleys in regard to resource usage. At one point the project manager needs 6 developers, but top management has made it very clear that she will not have access to more than 4. Classify this project in terms of the scheduling problem. What are the project manager's options at this point?

(Essay)
4.9/5
(23)

In terms of project classification, ________ constrained means that project duration is fixed and resources are flexible.

(Multiple Choice)
4.8/5
(40)

When there are not enough people, money, and / or equipment available for a project it is known as being

(Multiple Choice)
4.9/5
(34)

A project budget report is showing our project as spending $82,000 against a budgeted amount of $85,000. We can assume that everything is going as planned and that we are under budget.

(True/False)
4.9/5
(36)

Consider the following table of activities A through E in which A is the start node and E is the stop node.

(Multiple Choice)
4.9/5
(42)

Having too few programmers and too many engineers is an example of a people resource constraint.

(True/False)
4.9/5
(33)

In a resource-constrained project the third priority in assigning resources is usually given to activities with the

(Multiple Choice)
4.9/5
(36)

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

(Multiple Choice)
4.8/5
(39)

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

(Multiple Choice)
4.8/5
(40)

If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.

(True/False)
4.9/5
(35)

What are the impacts of resource-constrained scheduling?

(Essay)
4.8/5
(27)

Without a __________ budget a good project schedule and cost control are impossible.

(Multiple Choice)
4.8/5
(40)

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

(Multiple Choice)
4.8/5
(44)
Showing 101 - 114 of 114
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)