Exam 7: Managing Risk
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
The lowest risk value that an identified risk can take is ________, while the highest risk value that an identified risk can take is ______.
Free
(Multiple Choice)
4.8/5
(26)
Correct Answer:
A
The implications of an identified change need to be assessed by
Free
(Multiple Choice)
4.8/5
(48)
Correct Answer:
C
Based on the following, which event should you be most concerned about?
Free
(Multiple Choice)
4.7/5
(29)
Correct Answer:
B
Identify and briefly describe the five ways to respond to identified risks.
(Essay)
4.7/5
(33)
What is the difference between mitigating a risk and a contingency plan? Provide real life examples that illustrate the difference.
(Essay)
4.8/5
(36)
Responses to all identifiable risks should be a top priority for the project manager.
(True/False)
4.8/5
(25)
One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.
(True/False)
4.8/5
(31)
Why might an organization be opposed to developing and implementing a thorough risk management process?
(Essay)
4.8/5
(38)
Which of the following activities might you consider adding a time buffer to?
(Multiple Choice)
4.8/5
(37)
Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.
(Multiple Choice)
4.9/5
(30)
Opportunities identified within a project are treated very different from risks.
(True/False)
4.7/5
(31)
After your team has successfully identified potential risks that could affect the project, what is the next step?
(Multiple Choice)
5.0/5
(45)
Testing a new project on a smaller isolated area prior to installing it for the entire organization is an example of ________ a risk.
(Multiple Choice)
4.8/5
(37)
When considering risk management, what is an opportunity? List and briefly describe 5 different responses to an opportunity.
(Essay)
4.8/5
(36)
When considering risk value, the lower the value, the higher the level of risk.
(True/False)
4.8/5
(34)
According to the Failure Mode and Effects Analysis (FMEA), Impact × Probability × Detection = __________.
(Multiple Choice)
4.8/5
(37)
What is the purpose of using tools such as a risk assessment form and a risk severity matrix?
(Essay)
4.8/5
(37)
Give a real-life example of mitigating a risk, avoiding a risk, transferring a risk, escalating a risk and retaining a risk.
(Essay)
4.7/5
(42)
List the major response choices for negative risks. Do the same for positive risks (opportunities).
(Essay)
4.8/5
(31)
________ reserves are identified for specific work packages and are distributed by the project manager and the team members.
(Multiple Choice)
4.8/5
(24)
Showing 1 - 20 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)