Exam 6: Developing a Project Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A(n) ________ is the minimum amount of time a dependent activity must be delayed to begin or end.

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

B

Which of the following is NOT one of the basic rules to follow when developing project networks?

Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
Verified

C

Lags can be used to constrain the start and finish of an activity.

Free
(True/False)
5.0/5
(31)
Correct Answer:
Verified

True

The ________ calculates the earliest times that activities can start or finish.

(Multiple Choice)
4.8/5
(28)

Which of the following does NOT help describe a project network?

(Multiple Choice)
4.9/5
(41)

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

(Multiple Choice)
4.7/5
(37)

The delaying of any activity on the __________ will delay the completion of the project by the same amount.

(Multiple Choice)
4.9/5
(39)

What is the Concurrent Engineering Approach and why should project managers be aware of it?

(Essay)
4.8/5
(32)

The likelihood the original critical path(s) will change once the project is initiated is referred to as

(Multiple Choice)
4.9/5
(31)

The amount of time an activity can be delayed and yet not delay the project is termed

(Multiple Choice)
4.8/5
(37)

A(n) _________ activity has more than one dependency arrow flowing from it.

(Multiple Choice)
4.8/5
(33)

A purchasing agent is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, the purchasing agent has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. The purchasing agent and the installer share 10 days of

(Multiple Choice)
4.9/5
(27)

A(n) ________ activity has more than one successor activity.

(Multiple Choice)
4.9/5
(38)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.8/5
(29)

A _________ activity is one that has more than one activity immediately preceding it.

(Multiple Choice)
4.9/5
(29)

Activities that must immediately follow a given activity are called ________ activities.

(Multiple Choice)
4.8/5
(33)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.9/5
(38)

________ slack is the amount of time an activity can be delayed without delaying any immediately following (successor) activity can never be negative.

(Multiple Choice)
4.9/5
(30)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.8/5
(37)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

(Multiple Choice)
4.7/5
(37)