Exam 10: Being an Effective Project Manager
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection101 Questions
Exam 3: Organization: Structure and Culture102 Questions
Exam 4: Defining the Project112 Questions
Exam 5: Estimating Project Times and Costs95 Questions
Exam 6: Developing a Project Schedule128 Questions
Exam 7: Managing Risk105 Questions
Exam 8: Scheduling Resources and Costs114 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager98 Questions
Exam 11: Managing Project Teams103 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations102 Questions
Exam 13: Progress and Performance Measurement and Evaluation98 Questions
Exam 14: Project Closure97 Questions
Exam 15: Agile Project Management94 Questions
Exam 16: International Projects103 Questions
Select questions type
Give two advantages gained when a project manager takes the time to map relationship dependencies.
(Essay)
4.8/5
(32)
Once you have established who the key players are that will determine success, then you initiate contact and begin to build a relationship with those players. Less effective managers
(Multiple Choice)
4.7/5
(35)
_________-related currencies derive from people's burning desire to make a difference and add meaning to their lives.
(Multiple Choice)
4.8/5
(29)
In terms of commonly traded organizational currencies, sharing tasks that increase someone's skills and abilities and letting others have ownership and influence are examples of _______-related currencies.
(Multiple Choice)
4.9/5
(40)
One difference between project management and project leadership is that project management includes
(Multiple Choice)
4.7/5
(35)
Optimism, integrity, and even being proactive are not developed easily if there is not already a predisposition to display them.
(True/False)
4.7/5
(41)
Relationship-related currencies deal with the extent to which we can help others feel a sense of importance and personal worth by sharing tasks that increase their skills and abilities.
(True/False)
4.7/5
(34)
Experienced project managers recognize the need to build __________ before they need them.
(Multiple Choice)
4.8/5
(38)
Which of the following would be defined as the ability or skill to perceive, assess, and manage the emotions of one's self and others?
(Multiple Choice)
4.9/5
(40)
In regard to a network of stakeholders there are three "rings" or "tiers." Describe each ring and give an example of a group of stakeholders found in each.
(Essay)
4.9/5
(35)
________ naturally compete with each other for resources and support from top management.
(Multiple Choice)
4.8/5
(37)
The first step to building a social network is identifying those on whom the project depends for success.
(True/False)
4.9/5
(43)
One of the things that distinguish project management from regular management is the sheer breadth and complexity of the relationships that need to be managed.
(True/False)
4.9/5
(35)
Inspiration-related currencies derive from people's burning desire to make a difference and add meaning to their lives.
(True/False)
4.8/5
(27)
Once project managers have proven their _________ to upper management, senior management is much more receptive to their challenges and requests.
(Multiple Choice)
4.7/5
(36)
Management is about coping with complexity; ________ is about coping with change.
(Multiple Choice)
4.9/5
(40)
Stakeholders such as human resources, information systems, purchasing agents, and maintenance are typically classified as
(Multiple Choice)
4.7/5
(39)
People and organizations that are actively involved in the project, or whose interests may be positively or negatively affected by the project, are known as __________.
(Multiple Choice)
4.8/5
(43)
Showing 21 - 40 of 98