Exam 16: Scheduling
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?

(Multiple Choice)
4.8/5
(36)
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
Where in the optimum sequence should car E be scheduled?

(Multiple Choice)
4.8/5
(45)
The priority rule which will sequence jobs in the order they are received is
(Multiple Choice)
4.8/5
(31)
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?

(Multiple Choice)
4.9/5
(44)
Priority rules generally assume that job setup cost is independent of the processing sequence of jobs.
(True/False)
4.9/5
(38)
Priority rules are used in low-volume systems to identify an optimal processing sequence.
(True/False)
4.7/5
(33)
When operations are often bottlenecked, additional planned idle time will improve the throughput in those areas.
(True/False)
4.8/5
(36)
Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.
(True/False)
4.9/5
(37)
For the jobs listed below, which processing sequence would result using Johnson's rule?


(Multiple Choice)
4.8/5
(38)
The scheduling sequencing rule which always results in the lowest average completion (flow)time is the
(Multiple Choice)
4.8/5
(37)
Which of the following is not an example of a high-volume system?
(Multiple Choice)
4.8/5
(34)
Which costs depend on the order in which the jobs are processed?
(Multiple Choice)
4.9/5
(39)
Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of
(Multiple Choice)
4.8/5
(33)
In a task assignment situation, in how many different ways can five jobs be assigned to five machines if each job must be assigned to each machine and each machine must be assigned one job?
(Multiple Choice)
4.7/5
(40)
A schedule chart depicts the loading and idle times for a group of machines or departments.
(True/False)
4.8/5
(35)
_____ charts are often the preferred charts related to loading and scheduling activities.
(Multiple Choice)
4.8/5
(37)
The following matrix shows relative costs for various job-machine combinations. Assume there must be one-to-one matching between jobs and machines. Which set of pairs constitutes the minimum-cost solution using the assignment method?


(Multiple Choice)
4.8/5
(41)
Showing 61 - 80 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)