Exam 16: Scheduling
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
A Gantt chart is a basic scheduling tool that works best for high-volume systems.
(True/False)
4.8/5
(28)
Average completion (flow)time for a schedule sequence at a work center is
(Multiple Choice)
4.8/5
(39)
Line balancing is a major factor in the design and scheduling of low-volume systems because of batch processing.
(True/False)
4.8/5
(40)
The theory of constraints has a goal of maximizing flow through the entire system.
(True/False)
4.9/5
(31)
In an assignment model where there are fewer jobs than resources
(Multiple Choice)
4.7/5
(33)
The following table contains information about five jobs waiting to be processed at work center number three.
The sequence that would result using the SPT rule is

(Multiple Choice)
5.0/5
(36)
The quantity sent to a bottleneck operation could be split into two or more process batches to better utilize a bottleneck resource rather than process the entire batch.
(True/False)
4.8/5
(38)
The following table contains information about five jobs waiting to be processed at work center number three.
Using the EDD rule, the sequence of jobs would be

(Multiple Choice)
4.9/5
(33)
Splitting a large lot after one operation beyond a bottleneck operation would reduce the overall waiting time of the bottleneck operation.
(True/False)
4.9/5
(43)
The Hungarian method is limited to a maximum of two jobs per resource.
(True/False)
4.9/5
(34)
Which of the following is the last step in the capacity/scheduling chain?
(Multiple Choice)
4.7/5
(41)
_____ is a technique that managers can utilize in order to minimize the makespan for a group of jobs to be processed on two machines or at two work centers.
(Multiple Choice)
4.7/5
(36)
In theory of constraints scheduling, the __________ refers to the schedule and the __________ refers to inventory used to ensure that the bottleneck is never idle.
(Multiple Choice)
4.8/5
(37)
Which of the following is present in the manufacturing scheduling hierarchy but is absent in the service scheduling hierarchy?
(Multiple Choice)
4.9/5
(31)
The SPT priority rule always results in the lowest average completion time.
(True/False)
4.8/5
(34)
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
What is the idle time at the paint work center for the optimal schedule?

(Multiple Choice)
4.8/5
(40)
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
Where in the optimum sequence should car A be scheduled?

(Multiple Choice)
4.9/5
(43)
Ensuring that the constraining resource is used to its maximum is an example of constraint
(Multiple Choice)
4.9/5
(33)
Scheduling in service systems often takes the form of:
(I)appointment systems.
(II)reservation systems.
(III)makespan systems.
(Multiple Choice)
4.9/5
(47)
Showing 41 - 60 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)