Which of the following statements about learning curves is FALSE?

(Multiple Choice)
4.9/5
(29)

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 52 hours for the first widget.Acme estimates it has an 82% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 87th widget.

(Multiple Choice)
4.9/5
(32)

Purple Airlines has ordered 30 small jets from its supplier.The supplier has estimated the first aircraft will require 350 days of direct labor to manufacture and assemble.Based on past experience,the supplier estimates the learning curve to be 75%.Estimate the number of days of direct labor for all 30 jet aircrafts.

(Multiple Choice)
4.9/5
(33)

Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 15 iterations before the process reached a steady state of 27 hours.If Weston has a 94% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.

(Multiple Choice)
4.9/5
(44)

Which of the following statements is FALSE about limitations of learning curves?

(Multiple Choice)
4.7/5
(35)

Under the learning curve,as the number of repetitions or units of an item produced doubles,the processing time per unit of that item decreases by a constant percentage.This constant percentage is typically in the ______ range.

(Multiple Choice)
4.7/5
(36)

Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 18 iterations before the process reached a steady state of 6 hours.If Weston has a 78% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.

(Multiple Choice)
4.9/5
(31)

Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 11 iterations before the process reached a steady state of 18 hours.If Weston has a 95% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.

(Multiple Choice)
4.8/5
(38)

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 100 hours for the first widget.Acme estimates it has a 95% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 75th widget.

(Multiple Choice)
4.9/5
(45)

Learning curves are most useful for measuring performance improvements for ______.

(Multiple Choice)
4.7/5
(32)

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 62 hours for the first widget.Acme estimates it has a 98% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 56th widget.

(Multiple Choice)
4.8/5
(26)

Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 25 iterations before the process reached a steady state of 32 hours.If Weston has an 83% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.

(Multiple Choice)
4.9/5
(42)

The first unit produced in a process takes 480 hours.As the number of units produced doubles,production time decreases by 18%.Using the arithmetic approach,calculate the production time for the 64th unit.

(Multiple Choice)
4.9/5
(24)

Understanding learning curves will enable procurement specialists to determine the number of units of the specialized item that they plan to order and then negotiate with the supplier based on the order size.This statement is an application of learning curves in which of the following functions?

(Multiple Choice)
4.8/5
(33)

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 28 hours for the first widget.Acme estimates it has a 95% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the fourth widget.

(Multiple Choice)
4.9/5
(27)

A construction firm wants to estimate the direct labor of a worker who will perform multiple iterations of tasks.The worker must do a total of 20 of these activities to reach steady state.The time estimated to perform the 20th iteration is 2 hours,and the learning rate for this repetitive activity is 70%.The cost of labor is $40/hr.Estimate the direct labor cost for 20 iterations of these activities.

(Multiple Choice)
4.8/5
(39)

There are ______ approaches to solving learning curve problems.

(Multiple Choice)
4.9/5
(36)

Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 60 hours for the first widget.Acme estimates it has a 60% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 60th widget.

(Multiple Choice)
4.8/5
(30)

ABC Hospital completed its first transplant,and the procedure took 50 hours.The hospital has five more transplants scheduled.Based on other similar procedures carried out,the hospital estimates that it has an 85% learning rate.Estimate the time it will take to complete the third transplant.

(Multiple Choice)
4.8/5
(26)

______ is suitable only for estimating the number of hours required to produce the nth unit,where n is the doubled value.It cannot be used to find the time required to find intermediate units.

(Multiple Choice)
4.8/5
(29)