Exam 21: Master Scheduling and Material Requirements Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Item A has a lead time of 2 weeks and requires two units of Item B and three units of Item C.Item B has a lead time of 4 weeks; Item C has a lead time of 1 week.What should the planning horizon of the MRP be?

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
Verified

B

A method of representing the product hierarchy of a BOM file is the ______.

Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
Verified

C

Operations plans in the medium to short term are done during ______.

Free
(Multiple Choice)
4.7/5
(42)
Correct Answer:
Verified

D

When a company has a reputation of being environmentally unfriendly,______.

(Multiple Choice)
4.8/5
(26)

Which of the following is an output of MRP?

(Multiple Choice)
4.8/5
(38)

The master schedule ______.

(Multiple Choice)
4.9/5
(44)

The focus of the master schedule in an MTO production environment is ______.

(Multiple Choice)
4.9/5
(36)

The process of dividing the master scheduling planning horizon to allow for different rules for making changes is called ______.

(Multiple Choice)
4.8/5
(37)

What is the most important factor in choosing a lot-sizing technique?

(Multiple Choice)
4.8/5
(42)

Which of the following reports call for a manager's attention to major problems?

(Multiple Choice)
4.8/5
(43)

The production plan or procurement plan for raw materials and components for dependent demand items is done in ______.

(Multiple Choice)
4.7/5
(33)

The production plan or procurement plan for raw materials and components for independent demand items is done in ______.

(Multiple Choice)
4.7/5
(36)

Sufficiency of capacity for the output of the master schedule is checked during ______.

(Multiple Choice)
4.7/5
(42)

Materials requirements planning deals with products at what level?

(Multiple Choice)
4.9/5
(30)

An exception report is a ______ of the MRP process.

(Multiple Choice)
4.8/5
(34)

Updating or replanning the MRP records is performed periodically in which type of system?

(Multiple Choice)
4.8/5
(31)

In order for MRP implementation to be successful,______.

(Multiple Choice)
4.8/5
(30)

With regard to capacity planning,the difference between an integrated MRP-JIT system and an only-MRP system is that ______.

(Multiple Choice)
4.8/5
(30)

In lot-for-lot lot sizing,______.

(Multiple Choice)
4.8/5
(34)

The changes in firm planned orders ______.

(Multiple Choice)
4.9/5
(43)