Exam 4: Supplement: Project Management
Exam 1: Introduction to Managing Global Operations and Supply Chains97 Questions
Exam 2: Operations and Supply Chain Strategies99 Questions
Exam 3: Project Management100 Questions
Exam 4: Supplement: Project Management100 Questions
Exam 5: Product and Service Innovations100 Questions
Exam 6: Supplement: Reliability98 Questions
Exam 7: Managing for Quality100 Questions
Exam 8: Quality Improvement and Control Tools100 Questions
Exam 9: Capacity Planning100 Questions
Exam 10: Supply Chain Design and Location Planning100 Questions
Exam 11: Process Design and Layout Planning100 Questions
Exam 12: Supplement: Tools for Analyzing, Designing, and Selecting Processes and Layouts99 Questions
Exam 13: Supplier Management100 Questions
Exam 14: Logistics Management100 Questions
Exam 15: Demand Management and Customer Service100 Questions
Exam 16: Demand Forecasting Methods100 Questions
Exam 17: Lean Operations and Supply Chains99 Questions
Exam 18: Inventory Management100 Questions
Exam 19: Inventory Control Models100 Questions
Exam 20: Sales and Operations Planning99 Questions
Exam 21: Master Scheduling and Material Requirements Planning100 Questions
Exam 22: Supplement: Capacity Requirements Planning, MRP II, ERP, and DRP100 Questions
Exam 23: Detailed Scheduling100 Questions
Exam 24: Linear Programming100 Questions
Exam 25: The Transportation Models100 Questions
Exam 26: Waiting Line Models100 Questions
Exam 27: Simulation100 Questions
Exam 28: Learning Curves99 Questions
Exam 29: Decision-Making Tools100 Questions
Select questions type
Which of the following does NOT correctly pair the terminology used in the earned value management (EVM)method with its description?
Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
A
If the most optimistic and pessimistic times for a task are 3 and 15 days respectively,then the variance for the duration of the activity is ______.
Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
B
If the most optimistic and pessimistic times for a task are 3 and 11 days respectively,then the variance for the duration of the activity ______.
Free
(Multiple Choice)
4.8/5
(42)
Correct Answer:
B
Find the area under the normal curve between the Z values 0.65 and 2.07.
(Multiple Choice)
4.8/5
(33)
If the standard deviation is 3.4,the Z value is 1.95,and the expected date of completion is 38 months,then the due date for project completion is ______.
(Multiple Choice)
4.9/5
(43)
Find the area under the normal curve between the Z values 0.78 and 1.63.
(Multiple Choice)
4.8/5
(33)
If the standard deviation is 6.5,the Z value is 1.5,and the expected date of completion is 15 weeks,then the due date for project completion is ______.
(Multiple Choice)
4.8/5
(28)
The formula for the variance of the duration of an activity is ______.
(Multiple Choice)
4.8/5
(28)
If the standard deviation is 4.5,the Z value is 1.25,and the expected date of completion is 18 weeks,then the due date for project completion is ______.
(Multiple Choice)
4.8/5
(33)
If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 18 weeks is ______.
(Multiple Choice)
4.8/5
(38)
Whether we should crash an activity or not depends on ______.
(Multiple Choice)
4.8/5
(38)
Which of the following is NOT one of the types of probabilistic estimates used in PERT?
(Multiple Choice)
5.0/5
(33)
If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed within 90 days?
(Multiple Choice)
4.8/5
(35)
If the most optimistic time for completing an activity is 23,the most likely time is 25,and the most pessimistic time is 39,then the estimated time for the activity is ______.
(Multiple Choice)
4.9/5
(33)
If the most optimistic time for completing an activity is 2,the most likely time is 5,and the most pessimistic time is 8,then the estimated time for the activity is ______.
(Multiple Choice)
4.8/5
(36)
Find the area under the normal curve between the Z values 0.01 and 2.5.
(Multiple Choice)
4.7/5
(32)
The formula for the expected duration of an activity under these circumstances is ______.
(Multiple Choice)
4.9/5
(36)
Showing 1 - 20 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)