Exam 4: Supplement: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following does NOT correctly pair the terminology used in the earned value management (EVM)method with its description?

Free
(Multiple Choice)
4.9/5
(37)
Correct Answer:
Verified

A

If the most optimistic and pessimistic times for a task are 3 and 15 days respectively,then the variance for the duration of the activity is ______.

Free
(Multiple Choice)
4.8/5
(38)
Correct Answer:
Verified

B

If the most optimistic and pessimistic times for a task are 3 and 11 days respectively,then the variance for the duration of the activity ______.

Free
(Multiple Choice)
4.8/5
(42)
Correct Answer:
Verified

B

Find the area under the normal curve between the Z values 0.65 and 2.07.

(Multiple Choice)
4.8/5
(33)

If the standard deviation is 3.4,the Z value is 1.95,and the expected date of completion is 38 months,then the due date for project completion is ______.

(Multiple Choice)
4.9/5
(43)

Find the area under the normal curve between the Z values 0.78 and 1.63.

(Multiple Choice)
4.8/5
(33)

If the standard deviation is 6.5,the Z value is 1.5,and the expected date of completion is 15 weeks,then the due date for project completion is ______.

(Multiple Choice)
4.8/5
(28)

The formula for the variance of the duration of an activity is ______.

(Multiple Choice)
4.8/5
(28)

If the standard deviation is 4.5,the Z value is 1.25,and the expected date of completion is 18 weeks,then the due date for project completion is ______.

(Multiple Choice)
4.8/5
(33)

If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 18 weeks is ______.

(Multiple Choice)
4.8/5
(38)

Whether we should crash an activity or not depends on ______.

(Multiple Choice)
4.8/5
(38)

Which of the following is NOT one of the types of probabilistic estimates used in PERT?

(Multiple Choice)
5.0/5
(33)

If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed within 90 days?

(Multiple Choice)
4.8/5
(35)

If the most optimistic time for completing an activity is 23,the most likely time is 25,and the most pessimistic time is 39,then the estimated time for the activity is ______.

(Multiple Choice)
4.9/5
(33)

Project overhead costs ______.

(Multiple Choice)
4.8/5
(22)

The time-phased budget ______.

(Multiple Choice)
4.8/5
(32)

A project's baseline represents ______.

(Multiple Choice)
4.8/5
(40)

If the most optimistic time for completing an activity is 2,the most likely time is 5,and the most pessimistic time is 8,then the estimated time for the activity is ______.

(Multiple Choice)
4.8/5
(36)

Find the area under the normal curve between the Z values 0.01 and 2.5.

(Multiple Choice)
4.7/5
(32)

The formula for the expected duration of an activity under these circumstances is ______.

(Multiple Choice)
4.9/5
(36)
Showing 1 - 20 of 100
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)