Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________ method.
(Short Answer)
4.7/5
(31)
Ed is looking over the actual results of projects and comparing them to what was estimated.He notices that the projects that took six months or longer to complete were noticeably more off the estimates.Which of the following factors is he recognizing?
(Multiple Choice)
4.9/5
(40)
The consensus method of estimating costs is a bottom-up technique.
(True/False)
4.8/5
(31)
Cost,time,and budget estimates are the lifeline for control;they serve as the standard for comparison of the actual and the planned throughout the life of the project.
(True/False)
4.8/5
(31)
A good starting point for developing time and cost estimates is
(Multiple Choice)
4.9/5
(43)
Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs,outputs,inquiries,files,and interfaces.Which of the following methods is he using?
(Multiple Choice)
4.9/5
(33)
The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ___________ factor.
(Short Answer)
5.0/5
(34)
Which of the following is NOT true in regard to the level of detail estimates should contain?
(Multiple Choice)
4.8/5
(36)
Which of the following is NOT one of the factors that need to be considered to improve quality of estimates for project times and costs?
(Multiple Choice)
4.8/5
(45)
Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product.
(True/False)
4.8/5
(46)
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.He is using the ___________ method of top-down estimating.
(Short Answer)
5.0/5
(46)
Costs that are associated with time devoted to the coordination in meetings and briefings as well as time necessary to resolve disconnects between tasks are known as ____________ costs.
(Short Answer)
4.9/5
(38)
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself,____________ estimating is being used.
(Short Answer)
4.7/5
(40)
After averaging out the underestimates and overestimates,a long-duration project is more likely to be on target than a short-term,small project.
(True/False)
4.8/5
(40)
Laura is forecasting the time and cost of developing an intranet for a new customer.Her department has completed six such intranets for customers during the last two years.Although the proposed system is about the same size as the others,she estimates that it will take about 10 percent less time and money.Which of the following methods is she using?
(Multiple Choice)
4.8/5
(30)
The preferred method for situations involving strategic decision making,projects with a high degree of uncertainty,and projects with an unstable scope is the ___________ approach to estimating project time and costs.
(Short Answer)
4.8/5
(35)
The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as ____________.
(Short Answer)
4.8/5
(35)
If a project is internal to the company and relatively small,the bottom-up approach to estimating time and costs for the project is the best choice.
(True/False)
4.9/5
(37)
Past experience is almost always used primarily in the initial phases of estimating.
(True/False)
4.7/5
(35)
Refining estimates may be necessary for a number of reasons.For example,design flaws being revealed after the fact,extreme weather conditions,and accidents occurring are good examples of
(Multiple Choice)
4.8/5
(33)