Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
A way to improve estimates on future projects is to collect and archive data on past project estimates and actuals.Creating a ___________ for estimating is a way to achieve this goal.
(Short Answer)
4.9/5
(41)
Identify the three major categories of project costs and give an example of each.
(Not Answered)
This question doesn't have any answer yet
One guideline to follow when estimating time,cost and resources is to use several people to make the estimate for a task.
(True/False)
4.8/5
(39)
The process of forecasting or approximating the time and cost of completing project deliverables is called
(Multiple Choice)
4.7/5
(44)
Companies are using which of the following for improving the estimating process for future projects?
(Multiple Choice)
4.9/5
(42)
General and administrative costs are usually allocated as a percent of the total of a direct cost which includes labor,materials,or equipment.
(True/False)
4.8/5
(51)
What is the relationship between organizational culture and estimating?
(Multiple Choice)
4.8/5
(40)
If time and costs are important to a project the top-down approach to estimating time and costs for the project is the best choice.
(True/False)
4.8/5
(42)
List and describe two reasons why estimates may need to be refined.
(Not Answered)
This question doesn't have any answer yet
Reasons why estimating time and cost are important include all of the following EXCEPT
(Multiple Choice)
4.8/5
(40)
The salary of the project manager would be an example of what type of cost found in a project?
(Multiple Choice)
4.8/5
(38)
When someone uses experience and/or information from others to determine the project duration and total cost,____________ estimating is being used.
(Short Answer)
4.7/5
(37)
Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large?
(Multiple Choice)
4.8/5
(45)
Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete.Due to the uncertainty involved he will be making a low,an average and a high estimate.Rob is using which estimating approach?
(Multiple Choice)
4.9/5
(45)
The top-down method of estimating when the pooled experience of senior and/or middle managers are used to estimate the total project duration and cost is the _________ method.
(Short Answer)
4.7/5
(36)
Under what conditions would the top-down approach to estimating project times and costs be the best choice?
(Not Answered)
This question doesn't have any answer yet
Refining estimates may be necessary for a number of reasons.For example,resource shortages,in the form of people,equipment,or materials,can extend original estimates.This is a good example of
(Multiple Choice)
4.9/5
(36)
Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost.
(True/False)
4.9/5
(35)
The process of forecasting or approximating the time and cost of completing project deliverables is called planning.
(True/False)
4.7/5
(38)
Organization culture can significantly influence project time and cost estimates.
(True/False)
4.9/5
(42)
Showing 41 - 60 of 91
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)