Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
Project estimates should be broken down into as much detail,and with as much accuracy,as possible.
(True/False)
4.9/5
(42)
The preferred method for situations where the cost and time estimates are important,in a fixed contract situation,and when the customer wants a lot of detail is the ___________ approach to estimating project time and costs.
(Short Answer)
4.9/5
(34)
The estimating factor that considers the prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort is an example of the ___________ factor.
(Short Answer)
4.9/5
(42)
Which of the following is NOT one of the recommended guidelines for developing useful work package estimates?
(Multiple Choice)
4.9/5
(39)
The estimating factor that considers the skill level of participants doing the estimating is known as the ___________ factor.
(Short Answer)
4.9/5
(32)
The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.
(True/False)
4.9/5
(39)
Which of the following is a good condition for bottom-up estimating?
(Multiple Choice)
4.7/5
(35)
Estimating the total cost of a house by multiplying the total square feet by cost per square foot is an example of the apportion method of estimating costs.
(True/False)
4.9/5
(36)
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.Which of the following methods is he using?
(Multiple Choice)
4.7/5
(37)
Identify and briefly describe the two major classifications of estimating project time and costs.
(Not Answered)
This question doesn't have any answer yet
Identify and briefly describe three out of the six factors that should be considered to improve the quality of estimates for project times and costs.
(Not Answered)
This question doesn't have any answer yet
Showing 81 - 91 of 91
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)