Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

(Multiple Choice)
4.8/5
(34)

In order to shorten the duration of a project the project manager should limit the choices of activities to just those which are on the __________.

(Short Answer)
4.8/5
(37)

Cost slope can be determined by dividing the

(Multiple Choice)
4.8/5
(50)

Overhead costs such as supervision, administration, consultants, and interest are examples of ________ project costs.

(Short Answer)
4.9/5
(35)

When crashing an activity, you always crash to its crash point.

(True/False)
4.9/5
(35)

According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts?

(Multiple Choice)
4.8/5
(42)