Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

An activity's ________ is calculated by dividing the rise by the run.

(Short Answer)
4.9/5
(33)

_________ is the first thing to consider when deciding whether or not an activity can be crashed.

(Short Answer)
4.9/5
(47)

An activity's normal time and cost are 8 and $100, respectively.Its estimated crash time and cost are 6 and $160, respectively.What is this activity's crash cost per time unit?

(Multiple Choice)
4.8/5
(41)

There are more options available for reducing project time if you are not resource constrained.

(True/False)
4.8/5
(40)

Reducing the duration of an activity is called ________.

(Short Answer)
4.9/5
(39)

There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.

(Short Answer)
4.9/5
(38)

One way of reducing project costs is identifying tasks that _________ can do themselves.

(Multiple Choice)
4.8/5
(34)

For most projects, the estimation of a crash time is relatively easy.

(True/False)
4.7/5
(27)

A project that has several near-critical or critical paths is said to be

(Multiple Choice)
4.8/5
(32)

The higher the cost slope of an activity the lower the cost to reduce its duration.

(True/False)
4.8/5
(36)

Identify and briefly describe three out of the six reasons given in the text for attempting to reduce the duration of a project.

(Essay)
4.9/5
(31)

Crashing can negatively impact the morale and motivation of the project team.

(True/False)
4.7/5
(30)

The cost-time crashing method relies on choosing the cheapest method for reducing the duration of the project.What are other factors that should be assessed beyond simply cost?

(Essay)
4.9/5
(33)

When project managers know an activity's ________, they are able to compare which critical activities to shorten.

(Short Answer)
4.8/5
(31)

How would you calculate an activity's slope and what does it represent?

(Essay)
4.8/5
(42)

Adverse weather, design flaws, and equipment breakdown can create negative slack.This is an example of reducing project duration caused by

(Multiple Choice)
4.9/5
(34)

Which of the following projects would be least benefited if additional resources were added?

(Multiple Choice)
4.9/5
(36)

Why is the project duration with the lowest direct costs seldom the optimum duration for a project?

(Essay)
4.9/5
(39)

Why should a project manager be cautious when adding resources to reduce project duration?

(Essay)
4.7/5
(39)

When reducing project duration, the duration for a project that is optimal is at the point where

(Multiple Choice)
4.8/5