Exam 9: Reducing Project Duration

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

As a project is crashed and project duration is reduced, direct costs typically

(Multiple Choice)
4.7/5
(42)

Compressing activities on a project with a sensitive project network will:

(Multiple Choice)
4.9/5
(37)

The total cost for each time unit of a project is the sum of labor, materials, and equipment.

(True/False)
4.9/5
(39)

If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings.

(True/False)
4.9/5
(38)

When adding resources, there are limits as to how much speed can be gained.

(True/False)
4.7/5
(35)

Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.

(True/False)
4.8/5
(34)

One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making.

(True/False)
4.9/5
(28)

Resources are frequently over-allocated when crashing a schedule.

(True/False)
4.7/5
(40)

Which of the following is NOT considered a project indirect cost?

(Multiple Choice)
4.7/5
(42)

When crashing a schedule, this may set in when a least-cost method is used.

(Multiple Choice)
4.8/5
(37)

Which of the following is NOT a rational reason to reduce project duration?

(Multiple Choice)
4.9/5
(35)

When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.

(Short Answer)
4.8/5
(36)

Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by

(Multiple Choice)
4.8/5
(44)

Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by

(Multiple Choice)
4.9/5
(30)

It is going to cost $80,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska.This would be an example of a situation requiring reducing the project duration due to

(Multiple Choice)
4.8/5
(39)

The ________ project cost is the sum of the indirect and direct costs.

(Short Answer)
4.9/5
(35)

A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by

(Multiple Choice)
4.7/5
(30)

When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.

(True/False)
4.8/5
(42)

An activity must be crashed on each critical path in order to reduce project duration.

(True/False)
4.9/5
(37)

Given that an activity's normal time and cost are 10 days and $400, respectively, and its crash time and cost are 5 days and $800, respectively, what is the activity's slope?

(Essay)
4.7/5
(34)
Showing 41 - 60 of 106
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)