Exam 9: Reducing Project Duration
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
As a project is crashed and project duration is reduced, direct costs typically
(Multiple Choice)
4.7/5
(42)
Compressing activities on a project with a sensitive project network will:
(Multiple Choice)
4.9/5
(37)
The total cost for each time unit of a project is the sum of labor, materials, and equipment.
(True/False)
4.9/5
(39)
If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings.
(True/False)
4.9/5
(38)
When adding resources, there are limits as to how much speed can be gained.
(True/False)
4.7/5
(35)
Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.
(True/False)
4.8/5
(34)
One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making.
(True/False)
4.9/5
(28)
Resources are frequently over-allocated when crashing a schedule.
(True/False)
4.7/5
(40)
Which of the following is NOT considered a project indirect cost?
(Multiple Choice)
4.7/5
(42)
When crashing a schedule, this may set in when a least-cost method is used.
(Multiple Choice)
4.8/5
(37)
Which of the following is NOT a rational reason to reduce project duration?
(Multiple Choice)
4.9/5
(35)
When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.
(Short Answer)
4.8/5
(36)
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by
(Multiple Choice)
4.8/5
(44)
Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by
(Multiple Choice)
4.9/5
(30)
It is going to cost $80,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska.This would be an example of a situation requiring reducing the project duration due to
(Multiple Choice)
4.8/5
(39)
The ________ project cost is the sum of the indirect and direct costs.
(Short Answer)
4.9/5
(35)
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by
(Multiple Choice)
4.7/5
(30)
When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.
(True/False)
4.8/5
(42)
An activity must be crashed on each critical path in order to reduce project duration.
(True/False)
4.9/5
(37)
Given that an activity's normal time and cost are 10 days and $400, respectively, and its crash time and cost are 5 days and $800, respectively, what is the activity's slope?
(Essay)
4.7/5
(34)
Showing 41 - 60 of 106
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)