Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

(Multiple Choice)
4.7/5
(38)

System documentation cannot end until three days after testing has started.This is an example of which kind of lag?

(Multiple Choice)
4.9/5
(36)

It is possible for a project network to have more than one critical path.

(True/False)
4.8/5
(26)

A(n)________ is the minimum amount of time a dependent activity must be delayed to begin or end.

(Short Answer)
4.8/5
(32)

On a project network, the activity times are derived from the

(Multiple Choice)
4.8/5
(31)

In the network computation process what is a forward pass and what three things does it determine?

(Essay)
4.9/5
(34)

Which of the following will correctly calculate the total slack in an activity?

(Multiple Choice)
4.8/5
(43)

An activity cannot begin until ALL preceding connected activities have been completed.

(True/False)
4.7/5
(35)

Which of the following is NOT one of the basic rules to follow when developing project networks?

(Multiple Choice)
4.7/5
(34)

One piece of information that the arrows within the Activity-on-Node network can convey is

(Multiple Choice)
4.8/5
(38)

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

(Short Answer)
4.7/5
(34)

The ________ calculates the earliest times that activities can start or finish.

(Short Answer)
4.8/5
(29)

Negative slack can be estimated.

(True/False)
4.8/5
(36)

Only activities that occur at the end of a chain of activities can have free slack.

(True/False)
4.9/5
(44)

________ can never be negative and applies only to the last activity in a single chain of activities.

(Short Answer)
4.8/5
(27)

What is a Gantt chart and what advantages does it have over project networks?

(Essay)
4.8/5
(39)

In the network computation process what is a backward pass and what four things does it determine?

(Essay)
4.8/5
(32)

If the project has a duration of 13 days, the project should be completed 13 days from the day it starts.

(True/False)
4.9/5
(29)

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

(Multiple Choice)
4.9/5
(31)

Identify and briefly describe the four types of lags giving an example for each type.

(Essay)
4.8/5
(32)
Showing 21 - 40 of 105