Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A merge activity is one that merges with other activities into a succeeding activity.

(True/False)
4.9/5
(44)

The backward pass in project network calculations determines all of the following EXCEPT

(Multiple Choice)
4.8/5
(39)

It is acceptable for arrows to cross one another in a network diagram.

(True/False)
4.8/5
(29)

Which of the following does NOT help describe a project network?

(Multiple Choice)
4.8/5
(38)

A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity.

(Short Answer)
4.8/5
(32)

________ activities are to be completed immediately following a particular activity.

(Multiple Choice)
4.8/5
(29)

The likelihood the original critical path(s)will change once the project is initiated is referred to as

(Multiple Choice)
4.8/5
(38)

In a project network, recycling through a set of activities or __________ is not permitted.

(Short Answer)
4.8/5
(27)

A _________ activity is one that has more than one activity immediately preceding it.

(Multiple Choice)
4.8/5
(32)

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?

(Multiple Choice)
4.8/5
(27)

Gantt charts are popular because they represent an easy-to-understand, clear picture on a time-scaled horizon.

(True/False)
4.9/5
(36)

A(n)________ activity has more than one successor activity.

(Short Answer)
4.8/5
(35)

The backward pass determines project duration.

(True/False)
4.8/5
(30)

In a project network, ________ indicate activity dependency and project flow.

(Short Answer)
4.8/5
(31)

An element in the project that consumes time is a(n)___________.

(Short Answer)
5.0/5
(35)

Tom is responsible for ordering hardware for a custom home his company is building.The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days.Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer.He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days.Tom and the installer share 10 days of

(Multiple Choice)
4.7/5
(33)

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations.When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called

(Multiple Choice)
4.8/5
(40)

Activities that can occur while an activity is taking place are called ________ activities.

(Short Answer)
4.9/5
(38)

An activity that has more than one predecessor is a _________ activity.

(Short Answer)
4.7/5
(38)

When creating a project network, your primary input will be the

(Multiple Choice)
4.8/5
(36)
Showing 41 - 60 of 105