Exam 6: Developing a Project Plan
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
The delaying of any activity on the __________ will delay the completion of the project by the same amount.
(Short Answer)
4.8/5
(45)
Briefly describe looping and conditional statements and explain why they are not allowed when developing project networks.
(Essay)
4.8/5
(27)
Arrows on an activity-on-node (AON)project network represent
(Multiple Choice)
4.9/5
(34)
Activities that must immediately follow a given activity are called ________ activities.
(Short Answer)
4.9/5
(29)
A(n)__________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.
(Short Answer)
4.8/5
(40)
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
(Multiple Choice)
4.9/5
(34)
Within an Activity-on-Node network, the arrows depict activities to be accomplished.
(True/False)
4.8/5
(22)
___________ reflects the likelihood the original critical path(s)will change once the project is initiated.
(Short Answer)
4.8/5
(36)
The _________ lag is the most typical type of lag that is encountered in developing networks.
(Short Answer)
4.8/5
(30)
When completing a forward pass you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity.In this case you select the largest early finish number of all its immediate predecessor activities.Why do you select the largest early finish number?
(Essay)
4.8/5
(28)
The forward pass in project network calculations determines all of the following EXCEPT
(Multiple Choice)
4.8/5
(41)
Which of the following can be used without coordinating with managers of succeeding activities?
(Multiple Choice)
4.9/5
(32)
The forward pass through a project network determines the critical path.
(True/False)
4.9/5
(38)
The amount of time an activity can be delayed and yet not delay the project is termed
(Multiple Choice)
4.7/5
(33)
The activity time estimates used to build a project network are derived from ________.
(Short Answer)
4.9/5
(34)
Which of the following is provided by both the project network and the work breakdown structure?
(Multiple Choice)
4.9/5
(22)
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
(Multiple Choice)
4.9/5
(38)