The delaying of any activity on the __________ will delay the completion of the project by the same amount.

(Short Answer)
4.8/5
(45)

Briefly describe looping and conditional statements and explain why they are not allowed when developing project networks.

(Essay)
4.8/5
(27)

An activity can include only one work package.

(True/False)
4.7/5
(29)

Arrows on an activity-on-node (AON)project network represent

(Multiple Choice)
4.9/5
(34)

Activities that must immediately follow a given activity are called ________ activities.

(Short Answer)
4.9/5
(29)

A(n)__________ activity is frequently used to identify the use of fixed resources or costs over a segment of the project.

(Short Answer)
4.8/5
(40)

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

(Multiple Choice)
4.9/5
(34)

Within an Activity-on-Node network, the arrows depict activities to be accomplished.

(True/False)
4.8/5
(22)

A(n)_____________ calculates project duration.

(Short Answer)
4.8/5
(30)

___________ reflects the likelihood the original critical path(s)will change once the project is initiated.

(Short Answer)
4.8/5
(36)

The _________ lag is the most typical type of lag that is encountered in developing networks.

(Short Answer)
4.8/5
(30)

When completing a forward pass you carry the early finish to the next activity where it becomes its early start, unless the next succeeding activity is a merge activity.In this case you select the largest early finish number of all its immediate predecessor activities.Why do you select the largest early finish number?

(Essay)
4.8/5
(28)

Which of the following is true about hammock activities?

(Multiple Choice)
4.7/5
(41)

The forward pass in project network calculations determines all of the following EXCEPT

(Multiple Choice)
4.8/5
(41)

Which of the following can be used without coordinating with managers of succeeding activities?

(Multiple Choice)
4.9/5
(32)

The forward pass through a project network determines the critical path.

(True/False)
4.9/5
(38)

The amount of time an activity can be delayed and yet not delay the project is termed

(Multiple Choice)
4.7/5
(33)

The activity time estimates used to build a project network are derived from ________.

(Short Answer)
4.9/5
(34)

Which of the following is provided by both the project network and the work breakdown structure?

(Multiple Choice)
4.9/5
(22)

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

(Multiple Choice)
4.9/5
(38)