Exam 5: Estimating Project Times and Costs

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Typical kinds of costs found in a project include all of the following EXCEPT

(Multiple Choice)
4.7/5
(30)

Project costs such as labor and materials are typically classified as ___________ costs.

(Short Answer)
4.8/5
(42)

If time and costs are important to a project the top-down approach to estimating time and costs for the project is the best choice.

(True/False)
4.8/5
(37)

Describe phase estimating.When should it be used and how is it different from all other top-down and bottom-up methods of estimating?

(Essay)
4.9/5
(45)

The process of forecasting or approximating the time and cost of completing project deliverables is called planning.

(True/False)
4.8/5
(35)

Under what conditions would the bottom-up approach to estimating project times and costs be the best choice?

(Essay)
4.8/5
(43)

The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ___________ factor.

(Short Answer)
4.9/5
(37)

List and briefly describe four reasons why estimating time and cost are important to project management.

(Essay)
4.9/5
(33)

After averaging out the underestimates and overestimates, a long-duration project is more likely to be on target than a short-term, small project.

(True/False)
4.8/5
(32)

Project estimates should be broken down into as much detail, and with as much accuracy, as possible.

(True/False)
4.8/5
(39)

An external view of a Mega Project based upon the outcome of similar projects undertaken in the past is known as:

(Multiple Choice)
4.9/5
(39)

Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product.

(True/False)
4.8/5
(35)

Estimating the total cost of a house by multiplying the total square feet by cost per square foot is an example of the apportion method of estimating costs.

(True/False)
4.9/5
(36)

The estimating factor that considers the prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort is an example of the ___________ factor.

(Short Answer)
4.8/5
(43)

Estimates are supposed to be based on normal conditions.While this is a good starting point, it rarely holds true in real life.

(True/False)
4.9/5
(46)

The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.

(Short Answer)
4.9/5
(31)

The estimating factor that considers the skill level of participants doing the estimating is known as the ___________ factor.

(Short Answer)
4.9/5
(38)

Cost, time, and budget estimates are the lifeline for control; they serve as the standard for comparison of the actual and the planned throughout the life of the project.

(True/False)
4.8/5
(41)

What is the relationship between organizational culture and estimating?

(Multiple Choice)
4.9/5
(30)

Large projects that have long time horizons and a very high complexity can be referred to as

(Multiple Choice)
4.8/5
(30)
Showing 41 - 60 of 101
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)