Exam 5: Estimating Project Times and Costs
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
Costs that are associated with time devoted to the coordination in meetings and briefings as well as time necessary to resolve disconnects between tasks are known as ____________ costs.
(Short Answer)
4.8/5
(36)
Which of the following is NOT one of the factors that need to be considered to improve quality of estimates for project times and costs?
(Multiple Choice)
5.0/5
(38)
Under what conditions would the top-down approach to estimating project times and costs be the best choice?
(Essay)
4.8/5
(37)
A way to improve estimates on future projects is to collect and archive data on past project estimates and actuals.Creating a ___________ for estimating is a way to achieve this goal.
(Short Answer)
4.8/5
(42)
General and administrative costs are usually allocated as a percent of the total of a direct cost which includes labor, materials, or equipment.
(True/False)
4.8/5
(45)
Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.Which of the following methods is he using?
(Multiple Choice)
4.8/5
(44)
The consensus method of estimating costs is a bottom-up technique.
(True/False)
4.8/5
(28)
The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____________ method.
(Short Answer)
4.9/5
(34)
The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.
(True/False)
4.9/5
(38)
The salary of the project manager and temporary rental space for the project team would be classified as __________ costs.
(Short Answer)
4.9/5
(35)
The best way to __________________ is to collect and archive data on past projects.
(Short Answer)
4.8/5
(40)
The salary of the project manager would be an example of what type of cost found in a project?
(Multiple Choice)
4.9/5
(35)
One guideline to follow when estimating time, cost and resources is to use several people to make the estimate for a task.
(True/False)
4.8/5
(38)
The information necessary to conduct a bottom-up estimate of project time and costs starts with the ___________.
(Short Answer)
4.7/5
(33)
Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete.Due to the uncertainty involved he will be making a low, an average and a high estimate.Rob is using which estimating approach?
(Multiple Choice)
4.9/5
(35)
In practice, estimating processes are frequently classified as
(Multiple Choice)
4.7/5
(41)
The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as ___________.
(Short Answer)
4.9/5
(35)
Reasons why estimating time and cost are important include all of the following EXCEPT
(Multiple Choice)
4.7/5
(36)
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used.
(Short Answer)
4.7/5
(41)