Exam 7: Project Cost Management
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
Using simplified percentage complete amounts for a one-year project with weekly reporting and an average task or work packet size of one week,you can expect about a(n)____ percent error rate.
Free
(Multiple Choice)
4.9/5
(42)
Correct Answer:
A
Databases are a common tool for cost estimating,cost budgeting,and cost control.
Free
(True/False)
4.8/5
(35)
Correct Answer:
False
Using good _________________________ can change the false perception that costs grow and failures are to be expected.
Free
(Short Answer)
4.8/5
(32)
Correct Answer:
project cost management
Parametric models are least reliable when historical information was used to create the model.
(True/False)
4.9/5
(38)
A definitive estimate should be the least accurate of the three types of estimates.
(True/False)
4.8/5
(38)
The ____ is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project.
(Multiple Choice)
4.9/5
(41)
A ____ is done very early in a project or even before a project is officially started.
(Multiple Choice)
4.8/5
(35)
List and describe the three values calculated for an activity in earned value management.Give examples of each.
(Essay)
5.0/5
(28)
The people who develop software cost estimates often have a great deal of experience with cost estimation.
(True/False)
4.8/5
(35)
Many organizations now collect and control an entire suite of projects or investments as one set of interrelated activities in one place,called a(n)____________________.
(Short Answer)
4.9/5
(40)
____________________ considers the total cost of ownership,or development plus support costs,for a project.
(Short Answer)
4.8/5
(33)
Information technology project managers need to be able to present and discuss project information in ____________________ terms as well as in technical terms.
(Short Answer)
4.9/5
(32)
If cost variance is a positive number,it means that performing the work cost more than planned.
(True/False)
4.7/5
(34)
If a project manager gets sick for two weeks or an important supplier goes out of business,management reserve could be set aside to cover the resulting costs.
(True/False)
4.9/5
(31)
When deciding what projects to invest in or continue,you should include sunk costs.
(True/False)
4.8/5
(28)
____ is a method for determining the estimated annual costs and benefits for a project and the resulting annual cash flow.
(Multiple Choice)
4.8/5
(27)
If the cost estimate will be the basis for contract awards and performance reporting,it should be a ____ and as accurate as possible.
(Multiple Choice)
4.8/5
(33)
In practice,many people find that using a combination or hybrid approach involving analogous,bottom up,and/or parametric modeling provides the best ____________________.
(Short Answer)
4.8/5
(35)
The ____ is an estimate of the value of the physical work actually completed.
(Multiple Choice)
4.8/5
(34)
Showing 1 - 20 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)