Exam 7: Project Cost Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Using simplified percentage complete amounts for a one-year project with weekly reporting and an average task or work packet size of one week,you can expect about a(n)____ percent error rate.

Free
(Multiple Choice)
4.9/5
(42)
Correct Answer:
Verified

A

Databases are a common tool for cost estimating,cost budgeting,and cost control.

Free
(True/False)
4.8/5
(35)
Correct Answer:
Verified

False

Using good _________________________ can change the false perception that costs grow and failures are to be expected.

Free
(Short Answer)
4.8/5
(32)
Correct Answer:
Verified

project cost management

Parametric models are least reliable when historical information was used to create the model.

(True/False)
4.9/5
(38)

A definitive estimate should be the least accurate of the three types of estimates.

(True/False)
4.8/5
(38)

The ____ is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project.

(Multiple Choice)
4.9/5
(41)

A ____ is done very early in a project or even before a project is officially started.

(Multiple Choice)
4.8/5
(35)

List and describe the three values calculated for an activity in earned value management.Give examples of each.

(Essay)
5.0/5
(28)

The people who develop software cost estimates often have a great deal of experience with cost estimation.

(True/False)
4.8/5
(35)

Many organizations now collect and control an entire suite of projects or investments as one set of interrelated activities in one place,called a(n)____________________.

(Short Answer)
4.9/5
(40)

____________________ considers the total cost of ownership,or development plus support costs,for a project.

(Short Answer)
4.8/5
(33)

Information technology project managers need to be able to present and discuss project information in ____________________ terms as well as in technical terms.

(Short Answer)
4.9/5
(32)

If cost variance is a positive number,it means that performing the work cost more than planned.

(True/False)
4.7/5
(34)

If a project manager gets sick for two weeks or an important supplier goes out of business,management reserve could be set aside to cover the resulting costs.

(True/False)
4.9/5
(31)

When deciding what projects to invest in or continue,you should include sunk costs.

(True/False)
4.8/5
(28)

____ is a method for determining the estimated annual costs and benefits for a project and the resulting annual cash flow.

(Multiple Choice)
4.8/5
(27)

If the cost estimate will be the basis for contract awards and performance reporting,it should be a ____ and as accurate as possible.

(Multiple Choice)
4.8/5
(33)

____ should be forgotten.

(Multiple Choice)
4.8/5
(43)

In practice,many people find that using a combination or hybrid approach involving analogous,bottom up,and/or parametric modeling provides the best ____________________.

(Short Answer)
4.8/5
(35)

The ____ is an estimate of the value of the physical work actually completed.

(Multiple Choice)
4.8/5
(34)
Showing 1 - 20 of 100
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)