Exam 5: Project Scope Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

____ involves controlling changes to project scope throughout the life of the project,which is a challenge on many information technology projects.

Free
(Multiple Choice)
4.7/5
(34)
Correct Answer:
Verified

C

A WBS is often depicted as a task-oriented pie chart.

Free
(True/False)
4.9/5
(36)
Correct Answer:
Verified

False

The tasks in a WBS do not have to be developed as a sequential list of steps.

Free
(True/False)
4.8/5
(29)
Correct Answer:
Verified

True

It is easy to create a good WBS.

(True/False)
4.9/5
(42)

A project team always organizes the WBS around project products.

(True/False)
4.9/5
(35)

Many organizations provide guidelines and templates for developing WBSs.

(True/False)
4.8/5
(41)

Project scope statements should include,at a minimum,a product scope description and detailed information on all project deliverables.

(True/False)
5.0/5
(24)

____________________ is the difference between planned and actual performance.

(Short Answer)
4.9/5
(41)

Some project management experts believe that work should not be done on a project if it is not included in the _________________________

(Short Answer)
4.9/5
(39)

Key inputs for preparing the project scope statement include the ____________________,requirements documentation,and organizational process assets such as policies and procedures related to scope statements as well as project files and lessons learned from previous,similar projects.

(Short Answer)
4.9/5
(27)

The project scope statement should reference ____________________,such as product specifications that will affect what products are produced or purchased,or corporate policies,which might affect how products or services are produced.

(Short Answer)
4.9/5
(40)

Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

(True/False)
4.9/5
(36)

Many information technology projects also require detailed functional and design specifications for developing software,which also should be referenced in the detailed scope statement.

(True/False)
5.0/5
(36)

In the WBS,the main groupings for the work are listed in Level ____.

(Multiple Choice)
4.8/5
(34)

A(n)____________________ is a document that describes detailed information about each WBS item.

(Short Answer)
4.9/5
(32)

____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders,such as the customer and sponsor for the project,inspect and then formally accept the deliverables during this process.

(Multiple Choice)
4.8/5
(34)

____ involves formal acceptance of the completed project scope by the stakeholders.

(Multiple Choice)
4.8/5
(26)

The project scope statement provides the basis for planning and managing project schedules,costs,resources,and changes.

(True/False)
4.8/5
(41)

____________________ involves controlling changes to the project scope.

(Short Answer)
4.9/5
(39)

A unit of work should appear at only one place in the WBS.

(True/False)
4.7/5
(36)
Showing 1 - 20 of 75
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)