The critical path always includes the most critical activities.

Free
(True/False)
4.8/5
(34)
Correct Answer:
Verified

False

____ provide(s)a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
Verified

A

To make milestones meaningful,some people use the ____________________ criteria to help define them.

Free
(Short Answer)
4.8/5
(39)
Correct Answer:
Verified

SMART

A white diamond on the Tracking Gantt chart represents a(n)____________________.

(Short Answer)
4.8/5
(42)

The main outputs of ____________________ include work performance measurements,organizational process assets updates,such as lessons-learned reports related to schedule control,change requests,project management plan updates,and project document updates.

(Short Answer)
4.8/5
(31)

____ states that work expands to fill the time allowed.

(Multiple Choice)
4.8/5
(27)

The ____ is a network diagramming technique in which boxes represent activities.

(Multiple Choice)
4.8/5
(34)

The ____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

(Multiple Choice)
4.9/5
(34)

____________________ occurs when a resource works on more than one task at a time.

(Short Answer)
4.8/5
(31)

____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.

(Multiple Choice)
4.9/5
(39)

Different cultures may have different perceptions of work ethic.

(True/False)
4.8/5
(39)

____ involves controlling and managing changes to the project schedule.

(Multiple Choice)
4.8/5
(30)

Fast tracking can end up lengthening the project schedule.

(True/False)
4.7/5
(39)

Schedule performance can be estimated by subtracting the original time estimate from how long it really took to complete the project.

(True/False)
4.9/5
(33)

What are the basic reasons for creating dependencies among project activities? Describe each.

(Essay)
4.7/5
(29)

Most projects have one path through a network diagram.

(True/False)
4.8/5
(38)

The ____________________ is a tabulation of activities to be included on a project schedule.

(Short Answer)
4.9/5
(32)

A(n)____________________ is a schematic display of the logical relationships among,or sequencing of,project activities.

(Short Answer)
4.8/5
(38)

In a ____ relationship,the "from" activity must finish before the "to" activity can start.

(Multiple Choice)
4.9/5
(43)

____ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.

(Multiple Choice)
4.7/5
(47)