Exam 2: The Project Management and Information Technology Context
Exam 1: Introduction to Project Management100 Questions
Exam 2: The Project Management and Information Technology Context80 Questions
Exam 3: The Project Management Process Groups: A Case Study82 Questions
Exam 4: Project Integration Management100 Questions
Exam 5: Project Scope Management75 Questions
Exam 6: Project Time Management100 Questions
Exam 7: Project Cost Management100 Questions
Exam 8: Project Quality Management100 Questions
Exam 9: Project Human Resource Management100 Questions
Exam 10: Project Communications Management99 Questions
Exam 11: Project Risk Management99 Questions
Exam 12: Project Procurement Management75 Questions
Select questions type
Project managers have the most authority in a pure ____.
Free
(Multiple Choice)
4.9/5
(39)
Correct Answer:
B
Organizational issues are often the least difficult part of working on and managing projects.
Free
(True/False)
4.9/5
(31)
Correct Answer:
False
____ is a set of shared assumptions,values,and behaviors that characterize the functioning of an organization.
Free
(Multiple Choice)
4.7/5
(31)
Correct Answer:
C
Many companies have realized that information technology is integral to their business and have created a vice president or equivalent-level position for the head of information technology,often called the ____.
(Multiple Choice)
4.9/5
(40)
In a(n)____________________ organizational structure,project managers have little or no authority.
(Short Answer)
4.8/5
(37)
The ____ characteristic of organizational culture describes the degree to which management's decisions take into account the effect of outcomes on people within the organization.
(Multiple Choice)
4.9/5
(31)
In the ____ phase,the project team creates more detailed project plans,a more accurate cost estimate,and a more thorough WBS.
(Multiple Choice)
4.9/5
(32)
In early phases of a project life cycle,resource needs are usually ____ and the level of uncertainty is ____.
(Multiple Choice)
4.9/5
(37)
Project organizations may miss economies of scale available through the pooling of requests for materials with other projects.
(True/False)
5.0/5
(38)
The three spheres of systems management are business,organization,and ____________________.
(Short Answer)
4.8/5
(27)
____ is a problem-solving approach that requires defining the scope of the system,dividing it into its components,and then identifying and evaluating its problems,opportunities,constraints,and needs.
(Multiple Choice)
4.9/5
(41)
The ____ model requires heavy user involvement,and developers use a model to generate functional requirements and physical design specifications simultaneously.
(Multiple Choice)
4.8/5
(34)
A(n)____________________ is an overall model for thinking about things as systems.
(Short Answer)
4.9/5
(38)
The term ______________________________ has become popular to describe new approaches that focus on close collaboration between programming teams and business experts.
(Short Answer)
4.8/5
(41)
According to the symbolic frame,what is most important about any event in an organization is what actually happened.
(True/False)
4.8/5
(35)
It is rare for technical specialists or project managers to remain with the same company for a long time.
(True/False)
4.9/5
(38)
Management reviews,called phase exits or ____________________,are very important for keeping projects on track and determining if they should be continued,redirected,or terminated.
(Short Answer)
4.7/5
(29)
____ describes a holistic view of carrying out projects within the context of the organization.
(Multiple Choice)
4.9/5
(37)
Showing 1 - 20 of 80
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)