The Department of Motor Vehicle (DMV) testing center has ten (10) testers who test 75 drivers per day. Each tester can test eight (8) drivers per day. What would the service rate need to be in order to achieve 85% utilization?

(Essay)
4.7/5
(32)

Flow time is the average time an entity takes to complete one cycle of a process

(True/False)
4.8/5
(32)

A custom good or service is produced in anticipation of demand.

(True/False)
4.8/5
(37)

Which of the following is LEAST related to value stream mapping?

(Multiple Choice)
4.8/5
(36)

Which of the following is NOT a common process design improvement strategy?

(Multiple Choice)
4.7/5
(32)

Define a value stream map. How does this differ from a regular process map?

(Essay)
5.0/5
(36)

Little's Law states that Throughput = Flow Time × Work-In-Process.

(True/False)
4.7/5
(38)

What is the implied service rate per service-counter employee at an airport automobile rental counter if customer demand is 30 customers per hour, two service-counter employees are on duty, and their labor utilization is 65%?

(Essay)
4.7/5
(40)

A custom machine shop is able to process 40 orders per day. The average processing time is 5 days. What is the average number of orders that are in process at any time?

(Essay)
4.8/5
(27)

An order fulfillment process normally operates two shifts a day, six days per week. Under normal conditions, 380 orders can be processed per shift. What is the weekly capacity?

(Multiple Choice)
4.8/5
(45)

The decisions for the product-process matrix include all the following EXCEPT:

(Multiple Choice)
4.8/5
(38)

An automobile emission testing center has six (6) inspectors and tests 50 vehicles per hour. Each inspector can inspect twelve (12) vehicles per hour. What is the center's utilization?

(Multiple Choice)
4.8/5
(34)

What is the implied service rate per service-counter employee at an airport automobile rental counter if the customer demand is 36 customers per hour, two service-counter employees are on duty, and their labor utilization is 90%?

(Multiple Choice)
4.9/5
(38)

The service-positioning matrix focuses on the service encounter level rather than the overall design of the service system.

(True/False)
4.8/5
(32)

Some argue that modern technology invalidates the application of the product-process matrix. Explain their logic.

(Essay)
4.7/5
(46)

Standard goods are made in anticipation of customer demand and stocked in inventory and therefore, are usually available,

(True/False)
4.9/5
(31)