Exam 5: Developing the Schedule
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
A Gantt chart is the often the name for the network diagram tool for planning and scheduling.
(True/False)
4.8/5
(28)
When estimating resources for activities to estimate the activity's duration, the
(Multiple Choice)
4.7/5
(36)
The Scrum master is as a project manager in that he responsibility for the people on the development team.
(Multiple Choice)
4.7/5
(31)
This longest path in the overall network diagram is called the network path.
(True/False)
4.8/5
(40)
The sponsor or customer often states the project required completion time in the project charter, RFP, or contract.
(True/False)
4.9/5
(40)
It is necessary to monitor the progress to ensure that everything is going according to the plan.
(True/False)
4.9/5
(31)
The project control process starts with establishing a baseline plan that shows how the project scope will be accomplished on schedule and over budget.
(True/False)
4.8/5
(35)
An updated project schedule can be generated regularly that forecasts whether the project will finish ahead of or behind its required completion time.
(True/False)
4.9/5
(38)
If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data
(Multiple Choice)
4.7/5
(29)
Changes requested early in the project always have less impact on schedule and budget than if they are requested later in the project.
(True/False)
4.9/5
(43)
The earliest start time for a specific activity must be the latest of all the earliest finish times of all the activities leading directly into that specific activity.
(Multiple Choice)
4.9/5
(43)
Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
(Multiple Choice)
4.9/5
(41)
Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated occurrence.
(True/False)
4.8/5
(41)
Agile project management is an approach to product development time while risk through continuous interaction between the customer and small self-organizing teams that produce increments of working product.
(Multiple Choice)
4.9/5
(43)
Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
(Multiple Choice)
4.7/5
(43)
Latest start time LS) is the latest time by which a specific activity must be
(Multiple Choice)
4.9/5
(39)
The estimated activity resources will also be used later for estimating activity costs and determining the project budget.
(True/False)
4.8/5
(34)
As a part of the Scrum technique in agile project management, a sprint is usually one to four
(Multiple Choice)
4.8/5
(42)
Showing 41 - 60 of 86
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)