Exam 5: Developing the Schedule
Exam 1: Project Management Concepts79 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule86 Questions
Exam 6: Resource Utilization22 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organizational Structures65 Questions
Select questions type
The project team member also referred to as the customer representative and responsible for defining the customer requirements and product features and for ensuring that the development team delivers an end product with the required features is the
(Multiple Choice)
4.8/5
(30)
Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
(Multiple Choice)
4.8/5
(39)
When considering the availability of resources, it may be necessary to make some assumptions, such as
(Multiple Choice)
4.8/5
(35)
A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
(Multiple Choice)
4.9/5
(34)
Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
(Multiple Choice)
4.8/5
(29)
The ES and EF times are determined by calculating forward, that is, by
(Multiple Choice)
4.9/5
(44)