Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The project team member also referred to as the customer representative and responsible for defining the customer requirements and product features and for ensuring that the development team delivers an end product with the required features is the

(Multiple Choice)
4.8/5
(30)

Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

(Multiple Choice)
4.8/5
(39)

When considering the availability of resources, it may be necessary to make some assumptions, such as

(Multiple Choice)
4.8/5
(35)

A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that

(Multiple Choice)
4.9/5
(34)

Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.

(Multiple Choice)
4.8/5
(29)

The ES and EF times are determined by calculating forward, that is, by

(Multiple Choice)
4.9/5
(44)
Showing 81 - 86 of 86
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)