Burst activities are those with two or more successor activities.

(True/False)
4.8/5
(42)

  -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.8/5
(40)

Preceding activities are those that must occur before others can be done.

(True/False)
4.8/5
(25)

The variance of an activity is given by:

(Multiple Choice)
4.8/5
(37)

Serial activities are those that:

(Multiple Choice)
4.8/5
(34)

  -What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? -What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?

(Multiple Choice)
5.0/5
(33)

An activity has an optimistic time estimate of 17 days,a most likely estimate of 23 days,and a pessimistic estimate of 37 days.What is the variance of the activity?

(Multiple Choice)
4.9/5
(37)

  -Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. -Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.

(Multiple Choice)
4.7/5
(42)

Which technique would accelerate the completion of a project?

(Multiple Choice)
4.9/5
(28)

Use the information in the table to determine the slack time for Activity B. Use the information in the table to determine the slack time for Activity B.

(Multiple Choice)
4.9/5
(28)

Summaries for some subsets of the activities identified in the overall project network are called:

(Multiple Choice)
4.8/5
(40)

  -Which of these statements about this network is BEST? -Which of these statements about this network is BEST?

(Multiple Choice)
4.9/5
(33)

An activity has an optimistic time estimate of 12 days,a most likely estimate of 16 days,and a pessimistic estimate of 22 days.What is the expected standard deviation of the activity?

(Multiple Choice)
4.8/5
(27)

What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 - B 7 - D 8 A D 7 A E 4 B F 8 C, D G 9 E, F H 7 G

(Multiple Choice)
4.8/5
(35)

A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.

(True/False)
4.8/5
(32)

The PERT technique assumes that durations are more deterministic.

(True/False)
4.8/5
(35)

  -Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. -Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.

(Multiple Choice)
4.9/5
(41)

The overall effect of laddering activities is to:

(Multiple Choice)
4.8/5
(37)

  -Based on the activity network pictured,what is the BEST statement? -Based on the activity network pictured,what is the BEST statement?

(Multiple Choice)
4.7/5
(36)

A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity? Activity Optimistic time Most Likely time Pessimistic time Predecessor Corner Posts 4 5 6 - String Line 7 8 9 - Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Paint 9 11 Dig Holes, Plant Posts Tack Wire 9 12 16 Weld Top Bar

(Multiple Choice)
4.8/5
(31)