Exam 9: Project Scheduling: Networks,Duration Estimation,and Critical Path

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

  -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. -Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.

(Multiple Choice)
4.8/5
(36)

Use the information in the table to determine the late start time for Activity E. Early Early Late Late \cline 5-7 Task Predecessor Duration Start Finish Start Finish - 8 14 23 8 , 6 23 26 32 , 32 38

(Multiple Choice)
4.7/5
(38)

Use the values in the table to calculate activity durations and variances for the project.What is the likelihood of finishing this project within 47 days? Activity Predecessor Optimistic Likely Pessimistic A - 5 8 11 B A 15 20 25 D A 7 9 12 D A 12 16 20 F B, D 8 11 15 G C 13 17 22

(Essay)
4.9/5
(43)

A merge activity has two or more immediate predecessors.

(True/False)
4.9/5
(41)

Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal. Phoebe B.Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project.She calculated early and late start times and early and late finish times but spilled coffee all over her printout.Use the remaining information to reconstruct the table for Phoebe B.Beebee and her new canoe canal.

(Essay)
4.8/5
(36)

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity? Time Predecessor 7 8 13 8 7 6 6 11 12 14 ,,

(Multiple Choice)
4.8/5
(31)

  -Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. -Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.

(Multiple Choice)
5.0/5
(33)

The least amount of float is found:

(Multiple Choice)
4.9/5
(35)

Use the values in the table to calculate activity durations and variances for the project.What is the likelihood that the project takes between 60 and 55 days to complete? Use the values in the table to calculate activity durations and variances for the project.What is the likelihood that the project takes between 60 and 55 days to complete?

(Essay)
4.9/5
(41)

Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:

(Multiple Choice)
4.8/5
(36)

  -Based on the activity network pictured,what is the BEST statement? -Based on the activity network pictured,what is the BEST statement?

(Multiple Choice)
4.7/5
(40)

The late start time should be calculated using a forward pass through the network.

(True/False)
4.8/5
(36)

An activity has an expected duration and an expected cost.Another name for an activity is a(n):

(Multiple Choice)
4.8/5
(33)

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 - B 7 - 8 A 7 A E 4 B F 8 C, D G 9 E, F 7

(Multiple Choice)
4.7/5
(40)

Concurrent activities are:

(Multiple Choice)
4.9/5
(33)

What does a network diagram illustrate and why are they important in project management?

(Essay)
4.8/5
(35)

An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?

(Multiple Choice)
4.8/5
(32)

What is the slack time for Activity B given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5 -- B 7 -- C 8 A D 7 A E 4 B G 8 C, D H 9 E, F

(Multiple Choice)
4.7/5
(34)

These can be located by doing a backward pass through a network.

(Multiple Choice)
4.8/5
(40)

A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days)of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path? Activity Optimistic Most Likely Pessimistic time time time Predecessor Sorner Posts 4 5 6 - Dig Holes 10 12 14 Corner Posts Plant Posts 11 14 17 String Line Weld Top Bar 8 11 14 String Line Dig Holes, Plant Paint 9 11 13 Posts Tack Wire 9 12 16 Weld Top Bar

(Multiple Choice)
4.8/5
(27)
Showing 61 - 80 of 105